The first plan called for shutting down the 91 for 55 hours. Corona said no. So the team behind the SR-71/SR-91 Interchange Project rebuilt the job around overnight windows and live lanes, and the $137 million connector won an Award of Merit in Highway/Bridge in ENR’s 2026 West Best Projects awards on Oct. 26, 2026.
The Riverside County Transportation Commission owns the project, in partnership with Caltrans. Skanska USA Civil West built it, Parsons was civil engineer, and CHA Solutions served as construction manager. Construction started in January 2023, and the new connector opened to traffic in June 2025.
Project Scope
The interchange sits where Riverside, Orange and San Bernardino counties meet, and it carries commuters and freight between the 91 and the 71. The old eastbound 91 to northbound 71 move was a single-lane loop. It’s been replaced by a two-lane, non-tolled direct connector bridge that spans the 91 and the Santa Ana River. RCTC says the structure is about 100 feet tall and 2,500 feet long.
The work also added an eastbound 91 auxiliary lane, realigned the eastbound on-ramp from Green River Road and shifted southbound 71 to make room. Crews excavated about 400,000 cubic yards, placed more than 9 million pounds of rebar and built over 4,000 cubic yards of retaining walls. Funding came from federal, state and local sources, including Riverside County’s Measure A sales tax.
Why It Matters
The foundations are the real story. Condon-Johnson drilled the shafts, and differing site conditions showed up at four bents. Two more turned up obstructions that weren’t on any drawing, including an old sign foundation sitting inside the Bent 4 shaft and riprap with a drainage headwall at Bent 7. High groundwater at Bent 5 complicated permanent casing. Foundation work planned for about six months took nearly a year.
Instead of assembling a 270,000-pound casing and lifting it whole, crews set the first of six roughly 45,000-pound sections and welded the rest on in sequence from engineered platforms. That’s slower per shaft and far safer on a pick that size. They also set a 15-foot-diameter rebar cage with a 350-ton crane during overnight work.
Value engineering returned $1.3 million, per the ENR entry. For a corridor that RCTC finished designing in 2015 and couldn’t fully fund until December 2020, finishing in about two and a half years without the big closure is a decent result.
Related coverage & projects
Project Team & Details
| Owner / Client | Riverside County Transportation Commission |
|---|
| Consultants | Parsons (Civil Engineering) CHA Solutions (Construction Management) |
|---|
| General Contractor | Skanska USA Civil West |
|---|
| Major Subcontractors | Condon-Johnson (Deep Foundations) |
|---|
| Status | Completed |
|---|
| Delivery Method | Design-Bid-Build |
|---|
| Funding Source | Mixed |
|---|