Coast Guard Base Seattle Waterfront Modernization, Seattle
A construction project located in Seattle.

A Bit About Coast Guard Base Seattle Waterfront Modernization, Seattle
The Coast Guard is rebuilding its Seattle waterfront for icebreakers. Base Seattle, at Pier 36 on Elliott Bay, is the service’s West Coast hub for polar missions and home to Polar Star, Healy and Storis. Whiting-Turner now holds two contracts on the modernization: Phase 1A, awarded in August 2025 and worth up to $137.1 million, and Phase 1B, a $173.7 million award on Sept. 15, 2026. Commandant Adm. Kevin Lunday has put the service’s commitment to the base at $323 million.
Phase 1A was 26% complete when 1B was awarded, according to gCaptain. Both phases are scheduled to finish in fiscal 2029, with Phase 1C still in planning.
Project Scope
Phase 1A starts below the waterline. Crews are dredging Slip 36 and removing contaminated sediment under CERCLA and an EPA order. The Coast Guard calls the Pier 36 work the largest civil engineering and environmental remediation project in its history. The contract also widens the slip between Berths 36B and 37B, upgrades utilities at Berths 37A and 37B, demolishes a building and stabilizes the waterfront at Berth 36B. Station Seattle’s small boat docks and boathouse get recapitalized too.
Phase 1B builds a new pier at Slip 36B, with structural improvements, more dredging and utility and electrical upgrades. The first two phases produce two modernized major cutter berths sized for Polar Security Cutters. The longer plan covers berths for three Polar Security Cutters plus Healy, and the Coast Guard expects the first three phases done in 2030.
Phase 1B is paid for with fiscal 2025 budget reconciliation money. No designer has been named publicly.
Why It Matters
Pier 36 is now the whole plan. In April 2026 the Coast Guard dropped its pursuit of up to 53 acres at the Port of Seattle’s vacant Terminal 46, citing port economic impacts, environmental costs and conflicts with tribal fishing rights, and said it won’t seek more dock property in Seattle. Any West Coast icebreaker growth has to fit on the existing base footprint.
The berths may wait on the ships. The Coast Guard targets 2030 for its first heavy icebreaker, the future Polar Sentinel, but GAO has projected March 2033 for the lead Polar Security Cutter, estimated at about $3.4 billion. Sediment cleanup and pier work in Elliott Bay can’t be rushed, so building the waterfront first is the right order either way.
For Whiting-Turner, Seattle adds to a growing Coast Guard book. The firm also holds $116.7 million for Pier Mike at Base Charleston, about $69 million in hangars at Air Station Barbers Point and up to $400 million at Training Center Cape May. That’s a lot of waterfront and campus work with one federal client, and Seattle carries the most environmental exposure.
Related coverage & projects
Project Team & Details
| Owner / Client | U.S. Coast Guard |
|---|---|
| General Contractor | The Whiting-Turner Contracting Company |
| Status | Under Construction |
| Funding Source | Public (Federal) |
Where to find this project
Sorry, no records were found. Please adjust your search criteria and try again.
Sorry, unable to load the Maps API.
More images from Coast Guard Base Seattle Waterfront Modernization, Seattle
Related coverage & projects
Project Team & Details
| Owner / Client | U.S. Coast Guard |
|---|---|
| General Contractor | The Whiting-Turner Contracting Company |
| Status | Under Construction |
| Funding Source | Public (Federal) |