Gonzaga Ridge Wind Farm is what repowering looks like when the site fights back. Scout Clean Energy and general contractor Clark Bros. Inc. pulled 168 turbines dating to the 1980s off a ridgeline in Pacheco State Park near Los Banos, Calif., and replaced them with 25 modern machines producing a combined 150 MW, all while the park stayed open to the public. ENR named the job a Best Project in the Energy/Industrial category of its 2026 West Best Projects awards on Oct. 26, 2026.
The power is already spoken for. CleanPowerSF, San Francisco’s community choice program, contracted for the project’s 147.5 MW of wind plus a 50-MW, four-hour battery, and Peninsula Clean Energy signed a separate 15-year deal in 2021. Scout closed tax equity and debt financing for construction in July 2026, according to Latham & Watkins, which advised the developer.
Project Scope
The only way in was a 20-foot-wide road that had to be rebuilt while every crew, delivery and turbine component was still using it. NEI Electric Power Engineering led design, RRC handled structural, Fisher Associates did civil engineering, Bragg Cos. hauled and installed turbines and Hampton Tedder Electric took the high-voltage work.
Turbine pads were shrunk to limit disturbance in the park, but they still had to carry full seismic loads on a high-seismic site. Smaller pads meant less room for crane positioning and assembly, so the team checked the revised geometry against real equipment dimensions before mobilizing. When excavation hit hard rock where the design assumed grades could be cut to a 17% maximum, the team went back to state park officials for approval and added controlled drill-and-blast to the schedule.
Moving components uphill took Goldhofer trailers, blade lifters and prime movers on 17% grades. Deliveries ran just-in-time from an on-site transload yard, matching towers, nacelles and blades to installation readiness so parts never sat on sensitive ground. The site sits off State Route 152 with no interchange, so concrete went in at night under traffic control and turbine parts moved behind police escorts and rolling blockades.
Why It Matters
California’s oldest wind sites sit on some of its best wind, and most of them are still running 1980s hardware. Gonzaga Ridge is roughly a 7-to-1 reduction in turbine count for about nine times the original output, and it was done on state land, which makes it a template other repowers will be measured against.
It also shows where repowering cost hides. It isn’t in the turbines. It’s in access roads, rock, hauling and keeping a public park and a highway open while 25 sets of blades go up a ridge.
Related coverage & projects
Project Team & Details
| Developer | Scout Clean Energy |
|---|
| Owner / Client | Scout Clean Energy |
|---|
| Consultants | NEI Electric Power Engineering (Lead Design) Fisher Associates (Civil Engineering) RRC (Structural Engineering) |
|---|
| General Contractor | Clark Bros. Inc. |
|---|
| Major Subcontractors | Bragg Cos. (Turbine Hauling and Installation) Hampton Tedder Electric (High-Voltage Electrical) Vikor Teleconstruction (Trade Partner) ORR Protection (Fire Protection) Opoura (Trade Partner) Associated Tank Constructors (Tanks) CBI Power (Trade Partner) |
|---|
| Status | Completed |
|---|
| Funding Source | Private |
|---|