Texas pours more concrete than any other state, and the ground it pours onto is half the story. A wide band of expansive clay soils runs through the state's biggest population centers — the Blackland Prairie under Dallas–Fort Worth, Austin and San Antonio, and the notorious “gumbo” clays of greater Houston. These soils swell when wet and shrink hard in drought, which is why the post-tensioned slab-on-grade became the default Texas foundation, why engineered foundation designs based on a geotechnical report are standard on custom homes and commercial work, and why foundation repair is a large industry of its own here. When you hire a concrete contractor in Texas, you are hiring someone to manage soil movement as much as to place and finish concrete — and the difference shows up ten years later, not on pour day.
Heat is the other constant
Texas summers put concrete placement on a clock. High ambient temperatures, wind and low humidity accelerate set times and increase the risk of plastic shrinkage cracking, so experienced Texas crews schedule summer pours for dawn (or night, on big commercial placements), chill mix water, adjust mixes with retarders and supplementary cementitious materials, and treat curing as a specification item rather than an afterthought — the practices codified in ACI's hot-weather concreting guidance. A contractor who can explain their summer curing plan in plain language is usually a contractor whose slabs do not craze and dust two years in. Winter is the opposite problem only occasionally: hard freezes are rare but real, as the 2021 storm reminded everyone, and cold-weather protection matters a few weeks a year in North Texas and the Panhandle.
Who does what in the Texas market
The market splits into distinct segments. Residential flatwork and foundation contractors handle driveways, patios, slabs and repairs across every metro. Commercial concrete contractors — several of the country's largest are Texas-based — place tilt-wall panels, structural decks, paving and site concrete for the warehouses, data centers, plants and hospitals that dominate the state's construction pipeline; tilt-up construction in particular is a Texas staple for industrial and office product. Heavy-civil paving firms work TxDOT highway lettings and municipal programs. And a large ready-mix and materials industry — Texas is the biggest cement and ready-mix market in the country — supplies all of it. The current cycle is exceptional: semiconductor fabs around Austin and Taylor, data-center campuses across DFW, San Antonio and West Texas, petrochemical work on the Gulf Coast and relentless warehouse development all consume enormous concrete volumes, which keeps the best commercial crews booked and makes early contractor engagement worth real money on schedule.
Licensing works differently in Texas
Texas does not license general or concrete contractors at the state level — unlike electricians or plumbers, there is no state concrete license to check. Cities handle contractor registration and permitting locally, so vetting falls to you: verify liability insurance and workers' compensation coverage, ask for local references with projects old enough to show how the work has aged, and on structural scopes (foundations, retaining walls, elevated decks) expect an engineer's design and inspections rather than a handshake detail. For foundation repair, favor contractors who install to an engineer's repair plan and provide transferable warranties backed by an established company. On commercial work, prequalification does the same job: bonding capacity, safety record (EMR, OSHA logs), ACI-certified finishers and flatwork supervisors, and tilt-wall or post-tension track record comparable to your project.
What concrete work costs in Texas
Flatwork is usually priced per square foot, with thickness, reinforcement, finish and site access driving the spread; decorative finishes (stamped, stained, polished) price well above broom-finish gray. Foundation pricing rides the geotechnical report — pier depth and slab design vary street to street on expansive clays — and repair pricing scales with pier count. Material costs track cement and ready-mix markets, and quotes are typically firm for a limited window. Get itemized bids from two or three contractors, confirm who supplies the engineering, and be suspicious of any foundation bid produced without soil information.
Browse the concrete companies listed below, or pair your shortlist with general contractors and demolition specialists for full-scope work. Texas mega-projects and the firms building them are tracked in the Exchange projects directory — useful for seeing which concrete contractors are active on work like yours, from HVAC in Texas to structural trades.
How do mechanic's lien and retainage deadlines work for concrete contractors in Texas?
Payment security for Texas concrete work runs through Chapter 53 of the Texas Property Code, which House Bill 2237 rewrote with an effective date of January 1, 2022. The deadlines are counted in months, not days, and they differ between residential and other projects. An original contractor, meaning the concrete company hired directly by the owner, must file its lien affidavit with the county clerk no later than the 15th day of the fourth month after the month its work was completed, terminated or abandoned on commercial and industrial projects, and by the 15th day of the third month on residential construction projects. Subcontractors and suppliers file on the same fourth-month or third-month schedule, counted from the month they last provided labor or materials.
Subcontractors also have to give notice before they file. A concrete sub, a pump operator or a ready-mix supplier working under someone other than the owner must send a notice of claim for unpaid labor or materials to both the owner and the original contractor. On non-residential projects that notice is due by the 15th day of the third month after the month the work or materials were provided; on residential projects it is due by the 15th day of the second month. The statute prescribes the form of the notice, including its warning that the owner's property may be subject to a lien. Because each month of work starts its own clock, a foundation crew that pours footings in March and slabs in May has two separate notice deadlines. Tracking unpaid amounts month by month is the habit that protects lien rights in Texas.
Retainage is the other half of the system. During the work and for 30 days after the work under the original contract is completed, the owner must reserve 10 percent of the contract price, or 10 percent of the value of the work done. A claimant has a lien on those reserved funds only if it sent the required notices on time and filed its lien affidavit no later than the 30th day after the earliest of completion, termination or abandonment of the original contract. A subcontractor whose contract provides for retainage must also send a separate notice of claim for unpaid retainage, unless that retainage was already included in an earlier notice. That notice is due by the earlier of 30 days after the subcontractor's own contract is completed, terminated or abandoned, or 30 days after the original contract is terminated or abandoned. Concrete is usually one of the first trades on site and one of the first to finish, so this date often comes long before the building is done.
Filing the affidavit does not end the matter. A suit to foreclose the lien must be brought by the first anniversary of the last day the claimant could have filed its lien affidavit. The period can be extended to the second anniversary of the filing date only by a written agreement with the record owner, made before the first period runs out and recorded with the county clerk. Owners and general contractors should collect lien waivers with each pay application, and concrete subcontractors should put these dates in their calendar when they mobilize, not after a payment is missed.
What prompt-payment, bonding and workers' compensation rules apply to concrete contracts in Texas?
Chapter 28 of the Texas Property Code sets the prompt-pay rules on private projects. When an owner receives a written payment request for properly performed work, or for suitably stored or specially fabricated materials, it must pay the amount allowed under the contract, less any retainage the statute permits, within 35 days. A contractor that receives an owner's payment then has seven days to pay each subcontractor the portion attributable to that subcontractor's work. Unpaid amounts accrue interest at 1.5 percent per month from the day after payment was due. A party with a good-faith dispute may withhold no more than 110 percent of the disputed difference on a single-family home, duplex, triplex or quadruplex, and no more than 100 percent on other projects. Most attempts to waive these rules are void. The main exception allows a written contract for a single-family residence to give the owner a longer period, ending before the 61st day.
Chapter 28 also lets a contractor or subcontractor stop work. If the owner fails to pay an undisputed amount on time, the contractor or any subcontractor may suspend performance on the 10th day after giving written notice that payment has not been received and that it intends to suspend. The notice goes to the owner and, when there is a recorded construction loan that has funded the project, to the lender. For concrete crews, the threat of a suspension is often more effective than a lien, because a stopped pour holds up every trade behind it.
Public work runs on bonds instead. Under Chapter 2253 of the Government Code, a governmental entity must require the prime contractor to provide a performance bond on any contract over $100,000. A payment bond is required on contracts over $25,000, or over $50,000 when the owner is a municipality. Each bond is written for the full contract amount by a corporate surety. A concrete subcontractor or supplier that is not paid on a public job claims against the payment bond. To do that, it must mail written notice, with a sworn statement of account, to the prime contractor and the surety by the 15th day of the third month after each month in which the claimed labor or material was provided. Any unpaid retainage on the account must be listed in that statement.
Workers' compensation works differently in Texas. Under Labor Code section 406.002, most private employers may choose whether to carry it, so some concrete companies operate as non-subscribers, and owners on private work should check rather than assume coverage. On public projects there is no choice. Section 406.096 requires a governmental entity to have the contractor certify in writing that it covers every employee on the project. Each subcontractor must provide the same certificate to the general contractor, which passes it to the public owner. On residential jobs where the homeowner hires the concrete contractor directly, Property Code section 53.255 also requires the contractor to give the owner a statutory disclosure statement explaining lien rights and responsibilities before the contract is signed.
What stormwater, batch plant and silica rules apply to concrete work in Texas?
Site concrete work often triggers state environmental permits as well as a city permit. The Texas Commission on Environmental Quality regulates construction stormwater under the Texas Pollutant Discharge Elimination System Construction General Permit, TXR150000. The current permit took effect on March 5, 2023 and expires on March 5, 2028. TCEQ has started the renewal: it held a stakeholder meeting on June 9, 2026, and comments closed on June 23, 2026, so expect revised terms before the 2028 expiry. The permit applies to large construction activities that disturb five acres or more and to small construction activities that disturb at least one acre but less than five. It also covers smaller sites that are part of a larger common plan of development or sale reaching those thresholds. Sites under one acre that are not part of a larger common plan are not covered by this general permit.
For concrete contractors the practical effect is the stormwater pollution prevention plan. On covered sites, washout areas, slurry from saw cutting and the handling of curing compounds and form-release agents all have to fit the site's plan and inspection routine. Which party holds permit coverage depends on who controls the site, so concrete subcontractors should ask the general contractor or developer for the plan and follow its washout locations rather than improvising. Projects over the Edwards Aquifer recharge and contributing zones around San Antonio and Austin carry additional TCEQ requirements, and the agency directs anyone planning clearing or construction there to its regional offices before work starts.
Ready-mix and on-site batch plants need air authorization. TCEQ's Air Quality Standard Permit for Concrete Batch Plants is authorized under Health and Safety Code section 382.05195. A standard batch plant qualifies only if it produces no more than 650,000 cubic yards in any rolling 12-month period and no more than 300 cubic yards per hour. Dust at the central mix drum feed or truck drop point must be captured by a total enclosure or suction shroud, vented to a fabric filter baghouse moving at least 5,000 actual cubic feet per minute. Setback distances and other conditions also apply. Applications submitted on or after February 6, 2026 must use version 8.0 of form PI-1S-CBP through TCEQ's STEERS online system. Since May 1, 2025, operators relocating a temporary batch plant to a project site must notify the Air Permits Division through STEERS at least 12 business days before setting up.
Worker exposure to dust is regulated federally. Texas has no state OSHA plan, so the federal construction silica standard, 29 CFR 1926.1153, applies to saw cutting, grinding, core drilling and chipping concrete. It sets a permissible exposure limit of 50 micrograms of respirable crystalline silica per cubic meter of air as an 8-hour time-weighted average, with an action level of 25. Employers can comply either by measuring exposures or by fully implementing the engineering controls, work practices and respiratory protection listed for each task in Table 1 of the standard. In both cases they need a written exposure control plan covering the tasks, the controls, housekeeping and access restrictions. Ask any flatwork or cutting bidder for that plan.
Where can I verify a license and check the source in Texas?
Every figure and rule on this page can be checked against the primary source. These are the offices that publish them. Confirm current requirements directly before you rely on any of them:
Texas Legislature — Property Code Chapter 53, Mechanic's, Contractor's, or Materialman's Lien; Texas Legislature — Property Code Chapter 28, Prompt Payment to Contractors and Subcontractors; Texas Legislature — Government Code Chapter 2253, Public Work Performance and Payment Bonds; TCEQ — Stormwater General Permit for Construction Activities (TXR150000).
Concrete contractors in other regions: Florida, New South Wales, Ontario.
Other trades in Texas: Architect, Electrical, Engineer, Envelope, General Contracting, HVAC, Maintenance & Handyman, Mechanical, Plumbing, Renovation & Remodeling, Restoration, Roofing & Waterproofing, Windows and Doors.
Jump to licence verification sources for Concrete in Texas, or back to all concrete contractors on Exchange.