One Kane is an office building you can commute to by boat. The seven-story, 126,000-square-foot Class A project at 9551 East Bay Harbor Drive in Bay Harbor Islands topped out in October 2026, and developers Taubco and Landau Properties say it’s on track to deliver at the end of the first quarter or early in the second quarter of 2027. Civic Construction is the general contractor. Revuelta Architecture designed it.
There wasn’t any Class A office space on Bay Harbor Islands before this. The bet is that the executives who live in Bal Harbour, Surfside and Indian Creek would rather walk, drive or sail a few minutes to work than cross the causeway to Brickell.
Project Scope
The building sits on the Indian Creek Waterway, next to Bal Harbour Shops. Six office floors stack over a ground-floor restaurant, with floor plates running from about 12,600 to more than 18,300 square feet, 11-foot ceilings, floor-to-ceiling glass and a private terrace on every level. BondSt, the New York restaurant, has signed for the ground floor, and a rooftop bar overlooks the water.
The spec list reads like it was written for family offices and hedge funds: fiber-optic service, full-building standby power, impact-resistant glazing, flood-protected parking, valet and 24-hour secured entry. Along the seawall, plans call for eight private yacht slips managed by a full-time dockmaster. The project is planned for LEED certification.
Taubco and Landau closed a $74 million construction loan around the start of 2025 and broke ground that February. Vertical construction started in December 2025, so the concrete frame went up in about 10 months. With the superstructure done, crews have moved to the facade and glass enclosure, interior build-out and dock construction. Cushman & Wakefield is leasing the building.
Why It Matters
Miami’s office story since 2020 has been about migrating finance firms, and most of that demand landed in Brickell and Wynwood. One Kane tests whether a small, high-amenity building in a residential enclave can pull tenants away from the established cores. At 126,000 square feet it doesn’t need many leases to work.
For builders, the job is a reminder of what waterfront office work in South Florida now requires: flood-protected parking, hurricane glazing, backup power and marine construction folded into a single schedule. Those are becoming baseline items for coastal commercial work, not upgrades. The dock package is the part to watch as the project heads into 2027.
Related coverage & projects
Project Team & Details
| Developer | Taubco; Landau Properties |
|---|
| Owner / Client | Taubco and Landau Properties (joint venture) |
|---|
| Architect | Revuelta Architecture |
|---|
| Consultants | Cushman & Wakefield (Leasing) |
|---|
| General Contractor | Civic Construction |
|---|
| Status | Topped Out |
|---|
| Funding Source | Private |
|---|