The University of Kentucky isn’t paying for its newest clinic building up front. UK HealthCare broke ground Oct. 15, 2026, on the 220,000-square-foot Hamburg East Medical Office Building off Winchester Road in Lexington, a roughly $275 million outpatient center delivered as a public-private partnership with healthcare developer PMB.
Walsh Construction is the general contractor and Perkins&Will is the architect. Substantial completion is set for December 2028, with first patient visits targeted for spring 2029.
Project Scope
The building sits on Cowgill Way, on about 41 acres UK bought at the corner of Interstate 75 and Winchester Road (US-60). Lexington developer Cowgill Inc., the original landowner, handled site preparation starting in February 2024 and finished earlier this year. This first phase also includes parking, an arrival plaza and planted green space.
The program is wide. Adult and pediatric primary and urgent care sit alongside a musculoskeletal practice that puts orthopaedics, physical medicine and rehabilitation, and interventional pain in one place. Women’s health, ENT, ophthalmology, dermatology, cardiology, neurology and rheumatology fill out the specialty floors, with non-oncology infusion, imaging, labs and a drive-thru retail pharmacy. UK projects about 300,000 outpatient visits a year by 2034.
The deal structure is what’s unusual. PMB will plan, design, build, finance, operate and maintain the building. UK keeps the land and leases it to PMB for an initial 65 years, and PMB leases the finished building back to UK for 15 years, with renewal options.
Why It Matters
Academic medical centers are running out of room and borrowing capacity at the same time. UK HealthCare already logs more than three million outpatient visits a year, and Walsh is also building its 550,000-square-foot Cancer and Advanced Ambulatory Building on the main campus. Handing design, construction and financing of a $275 million clinic to a private partner, then leasing it back, lets the system keep both jobs moving.
There’s a cost to that, and it’s the lease. Fifteen years of rent on a building UK doesn’t own will add up, and the public hasn’t seen the payment schedule. But for a system that wants clinics where its employees and Eastern Kentucky patients actually live, the Hamburg site, ringed by I-75, I-64 and Baptist Health’s new campus, is hard to argue with.
Expect more P3 medical office deals like this from public universities that can’t wait for bond capacity.
Related coverage & projects
Project Team & Details
| Developer | PMB LLC |
|---|
| Owner / Client | University of Kentucky / UK HealthCare (land owner and tenant) |
|---|
| Architect | Perkins&Will |
|---|
| General Contractor | Walsh Construction |
|---|
| Major Subcontractors | Cowgill Inc. (Site Preparation) |
|---|
| Status | Under Construction |
|---|
| Delivery Method | Public-Private Partnership (P3) |
|---|
| Funding Source | Public-Private Partnership (P3) |
|---|