The University of Cincinnati kept the 1917 part of its Old Chemistry Building and tore off the 1930s part. That’s the decision that shaped the renovation and expansion, which ENR named the Best Project in higher education in its 2026 Midwest Best Projects awards on Nov. 9, 2026. Skanska USA Building and BHDP Architecture delivered it as a design-build team.
Old Chem reopened in September 2025 as a 207,000-square-foot home for chemistry teaching and research, shared by the College of Arts and Sciences, the College of Engineering and Applied Science and the James L. Winkle College of Pharmacy.
Project Scope
Crews fully renovated 63,000 square feet of the original 1917 building, demolished a 1930s addition and built a 144,000-square-foot structure connected to the old one. The work came in phased GMP packages: demolition, then site utilities and foundations, then structure and MEP, then fit-out.
The demolition package is where the surprise was. Crews found mercury in the 1930s addition, and abatement cost 40 days. The team recovered the time by redesigning on the fly so trades could work concurrently, and it still turned Phase 1 over two weeks early and Phase 2 three months early, according to the ENR entry.
THP Limited was structural engineer and Prater Engineering Associates handled MEP. O’Rourke Wrecking Co. ran demolition, with The Peck Hannaford + Briggs Co., Nelson Stark and Valley Interior Systems among the specialty contractors. A 1921 Rookwood tile fountain was pulled out, restored and reinstalled, and its chevron pattern shows up again in the interior window design. Bird-safe patterned glass and a rooftop pollinator garden round out the envelope.
Why It Matters
Lab buildings are among the hardest renovations there are, and they don’t get easier at 100 years old. Most universities facing a century-old science building just knock it down. UC didn’t. The project earned LEED Gold against a Silver target, cut energy use more than 25% against baseline and trimmed indoor water use 31.8%, per the Design-Build Institute of America. Early value engineering took $30 million out of the initial budget, and the job finished on budget.
The bigger lesson is about procurement. Hazardous materials hide in old lab buildings. A design-build team that can rework the sequence mid-demolition, without a change-order fight, is how a 40-day hit turns into an early finish.
Related coverage & projects
Project Team & Details
| Owner / Client | University of Cincinnati |
|---|
| Architect | BHDP Architecture |
|---|
| Consultants | THP Limited (Structural Engineering) Prater Engineering Associates (MEP Engineering) Resource International (Engineering) Julie Cromwell & Associates (Engineering) |
|---|
| General Contractor | Skanska USA Building |
|---|
| Major Subcontractors | O'Rourke Wrecking Co. (Demolition) The Peck Hannaford + Briggs Co. (Specialty Contractor) Nelson Stark (Specialty Contractor) Valley Interior Systems (Interiors) Facade Forensics (Facade Consultant) |
|---|
| Status | Completed |
|---|
| Delivery Method | Design-Build |
|---|
| Sustainability Certification | LEED Gold |
|---|
| Funding Source | Institutional |
|---|