Richardson ISD is done with junior highs. Cadence McShane Construction Co. has broken ground on the new Parkhill Middle School at 16500 Shadybank Drive in Dallas, a three-story, 201,209-square-foot building going up beside Parkhill Junior High on the same campus. The contractor announced the start in mid-October 2026 and expects to finish in December 2028.
Parkhill is one of six remaining junior highs the district is converting from grades 7-8 to grades 6-8 middle schools, a program funded by roughly half of the $1.4 billion bond voters approved in November 2025. Community Impact put the six transformations at $668 million, all running on the same two-year schedule.
Project Scope
Stantec is the architect of record. The building includes classrooms, collaborative learning areas, administrative offices, a library, a cafeteria, competition gyms and locker rooms. Site work adds a track, practice field, tennis courts and a courtyard plaza.
The new school is going up next to the existing junior high, so classes keep running in the old building during construction, though athletics have moved off site for now. Cadence McShane describes a multi-phase program built to keep the campus operating. Expect the usual occupied-campus headaches: separated construction access, phased utility tie-ins and a demolition sequence that can’t start until students move into the new building. Parkhill is one of four campuses, with Liberty, Westwood and Richardson West, that get brand-new buildings rather than additions.
Why It Matters
The 6-8 conversion isn’t cosmetic. Moving sixth grade out of elementary schools frees elementary seats, which RISD says could go to more pre-K, and lets the district run one middle school model. It also means every converted campus needs more capacity, more core space and bigger cafeterias and gyms. That’s why so many districts end up building new rather than adding on, especially with an average building age over 58 years.
Richardson ISD has been working through this list for a while. Lake Highlands and Forest Meadow started taking sixth graders in fall 2024. Cadence McShane, which says it’s worked for the district for more than two decades, built the 231,000-square-foot Lake Highlands Middle School. Repeat work on a program like this tends to pay off in faster preconstruction and fewer surprises, and trustees approved guaranteed maximum prices for five of the six projects in May with the total under budget.
The open question is schedule. Community Impact reported the conversions are aimed at fall 2028, but Cadence McShane’s December 2028 finish date means Parkhill’s new building may not be ready until the 2028-29 school year is underway. The district hasn’t said whether students would move midyear.
Project Team & Details
| Owner / Client | Richardson Independent School District |
|---|
| Architect | Stantec |
|---|
| General Contractor | Cadence McShane Construction Company |
|---|
| Status | Under Construction |
|---|
| Funding Source | Public (Municipal) |
|---|