Most school buildings hide their guts. The KRESA Career Connect Campus in Kalamazoo, Mich., puts them on display on purpose. The 162,000-square-foot career and technical education center, built by CSM Group and designed by DLR Group with Wightman as local architect, was named Best Project in K-12 Education in ENR’s 2026 Midwest Best Projects on Nov. 9, 2026.
The Kalamazoo Regional Educational Service Agency took ownership of the $100 million building in May 2025, held a public grand opening on May 22 and started classes that fall. It gives countywide CTE programs, once split across scattered sites, one home at 3500 Vanrick Drive next to Wings Event Center.
Project Scope
The campus holds 23 career pathways, 22 instructional labs and a greenhouse. Programs range from automotive technology, with equipment for hybrids, EVs and driver-assist systems, to a veterinary clinic, culinary kitchens, health science and a supply chain warehouse that comes with a forklift simulator. IMEG Corp. was structural engineer.
The frame is a hybrid of steel and mass timber, so students and the local trades get a daily look at a system that’s still uncommon in Michigan schools. Mechanical, electrical and IT systems are left exposed. Server racks in the IT labs can be seen from the commons, which lets students trace how conduit carries technology from one side of the building to the other.
Interiors were the hard part. Specialized labs piled up trade coordination, and the atrium drywall was difficult to reach. CSM’s team turned to lidar scanning, offsite precision cutting, QR-coded panel packs and robotic floor layout to eliminate cutting at height, reduce rework and speed installation, according to ENR.
Why It Matters
CTE demand in Michigan is at record levels. Architectural Record, citing the Michigan Department of Education, reported that 55,431 students completed CTE programs in the 2024-25 school year, the second straight record. Districts and intermediate agencies are under pressure to build space that feels like a workplace, not a shop wing tacked onto a high school.
Kalamazoo’s answer is a building that works as a teaching aid for the trades it’s trying to fill. That’s useful for the regional construction market as well. A teenager who’s spent a school year under exposed ductwork and timber beams has a better sense of what a jobsite career looks like than one who’s only seen drop ceilings.
The construction methods matter here too. Lidar, prefab panel packs and robotic layout aren’t exotic on a hospital or a data center anymore, but they’re still unusual on a school. CSM’s results give other K-12 owners a working example to point to when a GC proposes them.
Related coverage & projects
Project Team & Details
| Owner / Client | Kalamazoo Regional Educational Service Agency (KRESA) |
|---|
| Architect | DLR Group Wightman (Local Architect) |
|---|
| Consultants | IMEG Corp. (Structural Engineering) |
|---|
| General Contractor | CSM Group |
|---|
| Status | Completed |
|---|