Two pinch points in Worcester, Mass., stood between Norfolk Southern and a double-stack route into New England. The Worcester Clearance Improvement Project removed both, and on Nov. 5, 2026, ENR East named it Best Project in the Airport/Transit category.
The work sits on Providence and Worcester Railroad track, with Norfolk Southern as project sponsor and lead design firm. It’s one link in East Edge, the double-stack intermodal corridor NS opened between Chicago and Ayer, Mass., on Jan. 13, 2026, after a $64 million program of bridge raises, tunnel work and track renewal in Massachusetts and New York.
Project Scope
One restriction was an overhead bridge, cleared by lowering the track beneath it. Frontier Railroad Services handled that track lowering, with Frontier as prime contractor on the bridge location.
The other was harder: a roughly 2,000-foot stretch of steel-framed tunnel made up of two box culvert sections and the open track between them. There wasn’t room to raise anything, so the team went down. Crews micro-milled the tunnel floor to a controlled depth and replaced ballasted track with a direct fixation rail system, the kind usually seen on passenger lines, to squeeze out the vertical clearance double-stacks need. The milling was tuned to leave a uniform surface that met texture and smoothness requirements without extra coatings. RailWorks Track Services was prime contractor for the tunnel and its track lowering. AECOM served as civil and structural engineer, and AVP Engineering managed the project for P&W.
Nobody had as-built drawings of the tunnel. The team ran ground-penetrating radar surveys and laser scans to find every steel support beam, then turned that data into more than 8,000 custom anchor layouts that kept embedment depths and edge distances clear of the structure. According to the award entry, the contractor didn’t need a single field change to the design.
Why It Matters
New England has long been a single-stack island, which pushed freight onto trucks. Norfolk Southern says a fully double-stacked 9,000-foot train can support up to 200,000 loads a year through Ayer, a terminal that historically peaked around 80,000 lifts.
Worcester shows how corridors actually get cleared. It’s rarely a mega-project. It’s a handful of old structures, each owned by somebody different, each with its own permits and review cycle, and a tunnel nobody had drawings for. The engineering answer here was precision rather than demolition, and that’s a cheaper template for the next choke point.
Related coverage & projects
Project Team & Details
| Developer | Norfolk Southern Railway Co. (Project Sponsor) |
|---|
| Owner / Client | Providence & Worcester Railroad Co. |
|---|
| Consultants | Norfolk Southern Railway Co. (Lead Design) AECOM (Civil and Structural Engineering) AVP Engineering (P&W Project Manager) |
|---|
| General Contractor | RailWorks Track Services (Tunnels Prime Contractor) Frontier (Overhead Bridge Prime Contractor) |
|---|
| Major Subcontractors | Frontier Railroad Services (Overhead Bridge Track Lowering) |
|---|
| Status | Completed |
|---|
| Funding Source | Private |
|---|