Healdsburg hasn’t had passenger trains in nearly 70 years. Sonoma-Marin Area Rail Transit wants to fix that by the end of 2028. On Oct. 21, 2026, SMART’s board approved a $190.5 million construction contract with the Stacy and Witbeck/Herzog joint venture to push the commuter line north from Windsor into Healdsburg, the biggest step yet on an extension SMART pegs at $269 million all in.
The money is lined up. SMART calls the extension fully funded with $269 million in federal, state, regional and local grants, and the California Transportation Commission allocated $162 million in state grants the week before the award.
Project Scope
The joint venture isn’t new to the job. SMART picked it in September 2025 as general contractor and progressive design-build lead, with GHD running design and engineering and Modern Railway Systems handling signals and communications. RailPros, C&P, Stantec, Parikh, RSE and Pacific Railway Enterprises round out the team.
Most of the work is bringing a derelict rail segment back to life. Crews will rebuild the track on concrete ties and install modern train control, signaling and communications. Grade crossings get upgraded, and SMART’s multi-use pathway extends along the corridor for people on foot and bikes.
The two signature pieces are steel bridges that the contract covers from procurement through fabrication. A truss bridge will carry trains over the Russian River into Healdsburg, and a girder bridge will cross Old Redwood Highway. Both will also carry bike and pedestrian traffic, so the pathway doesn’t have to detour around either crossing.
What’s not in the contract is the station. SMART is weighing a downtown site against the historic depot area near Front Street, it’s taking public comment through Nov. 30, and the board is expected to pick a location in December. Active construction is set to start in spring 2027.
Why It Matters
Progressive design-build is doing real work here. Bringing the builder on during design let SMART lock its bridge strategy and long-lead steel before the station question was settled, instead of waiting on one decision to start the other. On a short line where two bridges drive most of the risk, that sequencing is the schedule.
It’s also how SMART keeps its northward march credible. Geyserville and Cloverdale come next on the map with no dates and no full funding. A Healdsburg opening on time and near budget is the strongest argument SMART will have when it goes back to grant programs for the rest.
Project Team & Details
| Owner / Client | Sonoma-Marin Area Rail Transit (SMART) |
|---|
| Consultants | GHD (Design and Engineering Lead) Modern Railway Systems (Signals and Communications) RailPros C&P Stantec Parikh RSE Pacific Railway Enterprises |
|---|
| General Contractor | Stacy and Witbeck/Herzog Joint Venture |
|---|
| Status | Planned |
|---|
| Delivery Method | Design-Build |
|---|
| Funding Source | Mixed |
|---|