Denton’s main wastewater plant dates to 1961, and the city is building its replacement right beside it. Sundt broke ground Sept. 22, 2026, on the Pecan Creek Water Reclamation Plant expansion, a construction manager at risk job that starts with a 75-million-gallon-per-day headworks and a 30-MGD treatment train built around membrane bioreactors.
Denton City Council awarded the CMAR contract in February under a first guaranteed maximum price of $92,321,565. That’s only the opening package. In 2025, design engineer Kimley-Horn told the city that building a new plant would cost about $498 million, roughly $133 million less than rehabilitating the old one, and other reports have since put the full program closer to $600 million.
Project Scope
The headworks comes first because everything downstream depends on it. At 75 MGD it’s sized far above the 30-MGD treatment train, which typically leaves room for wet-weather peaks and future phases. The MBR process replaces conventional clarifiers with membrane tanks, which shrinks the footprint and produces effluent clean enough for reuse.
Later packages add ultraviolet disinfection, anaerobic digesters and expanded solids handling, along with underground utility work, modifications to the existing chemical building and site improvements. A third GMP package went out for subcontractor bids this year.
The phasing rule is simple and strict: the existing plant stays fully operational and untouched while the new one goes up. Matt Bothun, Sundt’s Texas regional manager for water and wastewater, said the team is “keeping the existing facility fully operational” throughout. On a site where the current plant runs at about 85% of its 21-MGD rating, there isn’t much slack for outages.
Part of the cost is financed through the Texas Water Development Board’s Clean Water State Revolving Fund. The city approved a $60 million TWDB loan application in November 2025, which brings Build America, Buy America and American Iron and Steel requirements onto the job.
Why It Matters
Denton had about 150,000 residents in the 2020 census and could top 200,000 by 2030. Wastewater capacity is the kind of thing that stops development when it runs out, and the city is also starting design on a separate Clear Creek plant.
It’s part of a broader run of North Texas water work. Lewisville, San Marcos, Austin and Fort Worth have all let large treatment contracts in the last year. CMAR with multiple GMPs lets Denton lock in prices package by package instead of betting the whole program on one number, which matters when membrane systems, digesters and electrical gear all carry long lead times. The first GMP is the easy part. The digester and solids packages will show whether the program holds its budget.
Related coverage & projects
Project Team & Details
| Owner / Client | City of Denton |
|---|
| Consultants | Kimley-Horn (Design Engineer) |
|---|
| General Contractor | Sundt Construction |
|---|
| Status | Under Construction |
|---|
| Delivery Method | CMAR |
|---|
| Funding Source | Public (Municipal) |
|---|