Nobody flies into Austin to look at duct banks. Austin-Bergstrom International Airport broke ground on Oct. 19, 2026, on its Utility Infrastructure Campus-Wide project, known as UICW, a $344 million rebuild of the power, water, drainage and telecom systems under the airfield and terminal campus. Sundt Archer Western is the prime contractor and HDR is the designer, with completion targeted for 2029.
The project’s cost nearly tripled before the first shovel. City Council approved raising it from $120 million to $344 million on Oct. 22, three days after the ceremony.
Project Scope
UICW touches almost every system the airport runs on. The scope covers storm drainage, new stormwater and water-quality lines and detention ponds in the southwest part of the site, a new power distribution center with redundant medium-voltage distribution, hot- and chilled-water hydronic piping and duct banks for telecommunications and IT. The redundancy is the key piece. Days before the groundbreaking, a contractor struck an electrical line and knocked out part of the airport’s power. Airport Development Officer Rustin Roussel told the Airport Advisory Commission on Oct. 14 that UICW will bring electrical redundancy to all the buildings, “something we don’t necessarily have today.”
It’s also the enabling work for the rest of the Journey With AUS program. The airport has tied UICW directly to its New Central Utility Plant, the new Arrivals and Departures Hall and the Concourse B and tunnel project, all of which need the upgraded backbone before they can come online. Design started in 2024.
Why It Matters
The cost jump is the story. UICW was designed around 20 new gates. Then the airport finalized airline agreements for 32, with 26 at the future Concourse B and six at Concourse M, and every utility system had to be resized. A spokesperson said more funding authority will be needed as other Journey With AUS designs firm up, so this probably isn’t the last revision.
Funding comes from airline charges, airport cash reserves, revenue bonds and federal grants, with no city tax dollars, and the FAA has committed more than $16 million to UICW so far. The airport, which handles more than 20 million passengers a year now, is planning for 30 million to 35 million once expansion is complete.
Underground utility packages are where airport programs either hold their schedules or lose them. Building them early, while terminals are still in design, lets the vertical work start on a finished grid. Doing that on a live airfield, with tie-ins phased around flight operations, is the hard part Sundt and Archer Western are signing up for.
Related coverage & projects
Project Team & Details
| Owner / Client | City of Austin Department of Aviation (Austin-Bergstrom International Airport) |
|---|
| Architect | HDR (Designer) |
|---|
| General Contractor | Sundt Archer Western (Sundt Construction / Archer Western Construction) |
|---|
| Status | Under Construction |
|---|
| Funding Source | Mixed |
|---|