The Atlantic City Expressway third lane widening is finally moving. The South Jersey Transportation Authority held a ceremonial groundbreaking in Sicklerville, New Jersey, the week of Oct. 12, 2026, for a $400 million project to add a third lane in each direction on the toll road’s last two-lane stretch. That’s 12.6 miles between milepost 31.6 near Interchange 31 in Winslow Township and milepost 44.2 at the Route 42 terminus in Washington Township.
Don’t expect relief soon. Full completion is projected for 2034, and drivers won’t get to use the new lane until the whole thing is done.
Project Scope
The work goes well beyond paving. STV is leading final design for SJTA, and its scope covers a third lane through the Route 42 interchange, longer acceleration and deceleration lanes, improved geometry and removal of the middle-lane drop on the northbound side of that interchange. Bridge work includes mainline structures over Route 42 and the Great Egg Harbor River, widening the Route 42 bridge over Sicklerville Road and replacing the superstructure of the Sicklerville Road overpass to raise clearance.
The delivery plan is long and phased. SJTA describes a four-phase program, with advance work this fall, including widening the Exit 7 ramp to Sicklerville Road to two longer lanes. The first major roadway contract is slated for 2028 through 2030, and later contract dates haven’t been set. SJTA Chief Engineer Dan Corrigan said some final New Jersey DEP and Pinelands Commission approvals for larger segments are still pending. No construction contractor has been named for the widening.
Funding comes mainly from SJTA’s Transportation System Revenue bonds rather than state gas tax or general fund money, so expressway tolls carry the debt.
Why It Matters
Anyone who’s driven to the shore on a summer Friday knows this stretch. STV’s design work projects a 45% cut in traffic density and travel time savings through the Route 42 interchange of 55% westbound and 25% eastbound, compared with 2045 conditions if nothing gets built.
The cost history deserves a hard look. When Rep. Donald Norcross and SJTA promoted the third lane in 2022, local coverage put it at about $180 million with a possible 2025 start and roughly two years of work. It’s now $400 million, a 2026 groundbreaking and an eight-year runway. Some of that is honest scope growth around the interchange and bridges, and some is the inflation every highway agency has absorbed since. Either way, toll payers are funding more than twice the original number, and the ceremony came before the first big contract is even out to bid.
Related coverage & projects
Project Team & Details
| Owner / Client | South Jersey Transportation Authority |
|---|
| Consultants | STV Inc. (final design / engineering) |
|---|
| Status | Under Construction |
|---|
| Delivery Method | Design-Bid-Build |
|---|
| Funding Source | Public (State) |
|---|