A data center’s energization date set the clock on Aiken Sage Mill, and the clock didn’t move. Burns & McDonnell delivered the transmission program for Santee Cooper in Aiken County, S.C., on a compressed 15-month schedule, and ENR named it the Best Project in the energy/industrial category of its 2026 Texas & Southeast awards. Southeast winners were honored in Orlando on Oct. 23, 2026.
The work exists because a hyperscale data center needed high-capacity service. Santee Cooper, South Carolina’s state-owned utility, hired Burns & McDonnell as engineer-procure-construct contractor.
Project Scope
The scope had four pieces. Crews built a new 230-kV switching station, expanded an existing Santee Cooper substation from 115-kV to 230-kV, strung two new 230-kV transmission lines between the new station and the existing Aiken No. 3 substation, and rebuilt 16 miles of 115-kV line linking Aiken No. 1 with the Briggs Road and Aiken No. 3 substations.
Nearly all of it went into existing rights-of-way. That kept community and environmental impact down, but it made the job a brownfield one, with live transmission, distribution facilities and third-party utility crossings in the way. The team had to coordinate 39 separate transmission outages and hot-line work permits across several voltage levels.
Burns & McDonnell used a progressive EPC model in two phases. Phase 1 fixed scope, cost and schedule while engineering kept moving and long-lead equipment got ordered. Phase 2 priced materials and construction and bought out the subcontracts quickly. Woodson Tree, Forbes Bros., Timberline Construction, Great Southwestern Construction and Resa Service worked as subcontractors. Construction started in August 2024.
Why It Matters
Outages are the real constraint on brownfield transmission, and this team built a process around them. Outage requests had to be locked weeks ahead so Santee Cooper could plan crews and check grid impact. When communication gaps started threatening critical-path work, the team stopped patching them one at a time and set up a structured outage tracking and reporting framework that ENR calls a repeatable model for future jobs.
The safety and cost numbers hold up as well. The project logged 270,000 worker hours without an OSHA recordable incident and finished at budget and ahead of schedule.
Utilities across the Southeast are getting the same request from data center developers: big load, fixed date. Reusing existing corridors and running progressive EPC is how Santee Cooper hit one. Expect more utilities to try the same approach.
Project Team & Details
| Owner / Client | Santee Cooper |
|---|
| General Contractor | Burns & McDonnell |
|---|
| Major Subcontractors | Woodson Tree LLC (Vegetation Management) Forbes Bros. (Transmission Line) Timberline Construction Inc. (Subcontractor) Great Southwestern Construction Inc. (Transmission Line) Resa Service LLC (Subcontractor) |
|---|
| Status | Completed |
|---|
| Delivery Method | Design-Build |
|---|
| Funding Source | Public (State) |
|---|