Chobani is acquiring a food manufacturing plant in Allentown, Pennsylvania from Keurig Dr Pepper for $125 million and investing a total of $1.2 billion in the site over five years. The facility opened in 2021. Chobani describes it as a major new hub for the company’s growth, and expects it to create more than 900 jobs.
Project Scope
Plans call for up to 10 production lines and a campus of roughly 1.5 million square feet of manufacturing and warehouse space within five years. Production will centre on milk with higher protein and lower sugar than conventional milk, feeding high-protein shakes and related products, which makes this a process fit-out rather than a simple capacity addition.
The gap between the $125 million purchase price and the $1.2 billion programme is the tell. The building is already there; what the capital buys is process equipment, utilities, clean design and the warehouse expansion around it.
The expansion also proceeds around live production. Chobani will continue manufacturing some products for Keurig Dr Pepper at Allentown for a period after the sale, so process piping, utility tie-ins and sanitary work have to be phased against an operating plant. That constraint tends to push work into short shutdown windows and raises the coordination burden well above a greenfield equivalent.
Why It Matters
The site sits within 500 miles of roughly 40% of the U.S. population, and at full capacity is expected to source more than 3 billion pounds of Pennsylvania milk a year. That ties the investment to a regional dairy supply chain rather than a national one, and it gives the plant a catchment argument that a greenfield in a cheaper state could not match.
Allentown is part of a stated $4 billion-plus U.S. manufacturing program that already includes $500 million at Twin Falls, Idaho and $1.2 billion at Rome, New York. Food and beverage remains one of the few industrial segments committing capital at this scale while broader manufacturing construction contracts, which makes owners like Chobani unusually important to industrial contractors’ backlogs right now.
Related coverage & projects
Project Team & Details
| Developer | Chobani |
|---|
| Owner / Client | Chobani |
|---|
| Status | Planned |
|---|
| Funding Source | Private |
|---|