Pendry Tampa has topped out. The 38-story tower on downtown Tampa’s Riverwalk combines a 218-room Pendry hotel with 190 Pendry Residences, and developer Two Roads Development announced the milestone in mid-October 2026. Coastal Construction is the general contractor, and Arquitectonica designed the building.
Project Scope
The tower sits at 103 Ashley Drive South, at Ashley and Whiting, on a tight riverfront lot. The hotel occupies the lower floors, with the branded condominiums above and a residents-only rooftop pool on the 38th floor. Hotel guests get their own 12th-floor pool deck.
The hotel program includes a signature restaurant, a Mexican concept, a speakeasy lounge, a poolside restaurant, Spa Pendry, a fitness center and more than 14,000 square feet of meeting and event space. Clique Hospitality runs food and beverage. Studio Munge did the interiors, and Kimley-Horn is landscape architect. C&C Concrete Pumping partnered with Coastal on the vertical concrete.
The unit counts have moved around since launch. The 2023 announcement called for 220 rooms and 207 residences, a 2024 update said 212 residences, and the topping-out release lands at 218 and 190. That’s normal for a branded tower selling during construction, as buyers combine units and the hotel program gets refined.
Two Roads says more than 80% of the residences are under contract, representing over $400 million in sales, with prices starting around $1.7 million.
Why It Matters
Downtown Tampa has added luxury hotel keys and condos fast since Water Street opened the east side of the core. Pendry is a bet that the Riverwalk side can support the same pricing.
The schedule is the caution. When ground broke in late 2023, completion was pegged at the second quarter of 2026. The hotel is now expected to open in 2027. Two Roads hasn’t explained the slip publicly, though the topping-out release mentions engineers working through geological and subsurface problems on the site. Building a 38-story tower right at the river’s edge in Tampa means dealing with karst limestone and a high water table, and foundation work there rarely goes quickly.
With most of the residences presold, the financial risk is lower than the delay suggests. The open question is whether the hotel can command Miami-level rates on the Hillsborough.
Project Team & Details
| Developer | Two Roads Development (with Pendry Hotels & Resorts / Montage International) |
|---|
| Architect | Arquitectonica |
|---|
| Consultants | Studio Munge (Interior Design) Kimley-Horn (Landscape Architecture) |
|---|
| General Contractor | Coastal Construction |
|---|
| Major Subcontractors | C&C Concrete Pumping (Concrete) |
|---|
| Status | Topped Out |
|---|
| Funding Source | Private |
|---|