The Four Seasons Hotel and Residences Charleston finally has a builder. Strategic Property Partners named Hoar Construction general contractor in September 2026 for South Carolina’s first Four Seasons, a 139-room hotel with 36 private residences on the old Days Inn site at 155 Meeting Street. The catch is the calendar: completion is now targeted for 2030, two years later than the 2028 date the developer was using not long ago.
SPP is the Tampa developer behind Water Street, and its capital partner here is Cascade Investment, Bill Gates’ holding company, which also controls the Four Seasons chain. That’s an unusual alignment of owner, money and brand on one deal, and it explains why a project this size can absorb a two-year slip without changing its basic program.
Project Scope
The 1.9-acre site sits in the middle of the peninsula’s historic district, near Horlbeck Alley. The Days Inn came down in February 2026 after demolition slid from late 2025. Earlier planning documents reviewed by Charleston’s Board of Architectural Review described three buildings rising as high as eight stories, with all parking moved below grade after the developer dropped an above-ground garage from the tallest building.
Morris Adjmi Architects is the architect, with Lark Design Studio and Hollander Design on the team. Iskagna, a Charleston firm, is owner’s representative.
The program goes well past a room block. Plans call for several restaurants and bars, a spa and fitness center, an outdoor pool and about 7,000 square feet of event space. The residences run from roughly 1,700 square feet for a one-bedroom to about 3,700 square feet for a three-bedroom, with prices starting at $5 million. Owners have spent about $57 million assembling the site and neighboring downtown parcels. No construction cost has been disclosed.
Groundbreaking is expected by the end of 2026.
Why It Matters
Charleston’s design review process is famously slow, and this job has already been through it more than once. After winning final approval from the Board of Architectural Review, the team went back to the board with revisions that moved parking underground and shifted the room and residence counts.
For Hoar, the Birmingham-based builder, it’s a marquee hospitality job on one of the tightest urban sites in the Southeast. Underground parking on the peninsula means digging near the water table in a city that expects archaeology on sites like this, and the developer has already lined up stormwater upgrades and archaeological work ahead of vertical construction.
The schedule slip is the number to watch. Demolition delays and contractor selection pushed completion from 2028 to 2029, then to 2030. Branded residences at $5 million and up can carry a lot of carrying cost. Four years of it is still a test.
Project Team & Details
| Developer | Strategic Property Partners |
|---|
| Owner / Client | Strategic Property Partners (with capital partner Cascade Investment LLC) |
|---|
| Architect | Morris Adjmi Architects |
|---|
| Consultants | Lark Design Studio (Design) Hollander Design (Landscape Architecture) Iskagna (Owner's Representative) |
|---|
| General Contractor | Hoar Construction |
|---|
| Status | Planned |
|---|
| Funding Source | Private |
|---|