Atari Hotels Phoenix is the kind of project that’s easy to dismiss as a licensing stunt, right up until the excavators show up. Intersection Development started construction the week of Oct. 29, 2026, on the gaming-themed hotel and entertainment venue at 840 N. Central Ave. in Phoenix’s Roosevelt Row arts district, with completion targeted for late 2028 or early 2029.
The first phase is demolition. A two-story building on the site, home to KOOL radio starting in 1957 and later to KOY, KMLE, Y94 and KZON, is coming down so crews can prepare the ground for the hotel’s foundation. Phase 2, the vertical build, is expected to follow shortly after.
Project Scope
The program packs a lot onto less than an acre. Construction Reporter and AZ Big Media put the cost at $124 million for a roughly 90,000-square-foot building with 72 rooms and 19 suites, a count that nods to Atari’s 1972 founding. The headline space is a two-level concert and esports venue on a main floor plus mezzanine. Its capacity has crept upward across announcements, from 2,000 to 2,200 to the roughly 2,400 the developer cited at groundbreaking.
The rest of the building stacks a sportsbook, a sports-viewing hub with more than 200 screens, creator studios, restaurants, bars, retail and a pool deck. A penthouse suite with its own pool sits on top. Phoenix-based räkkhaus designed the tower as a glowing, pixel-patterned mass with an LED-wrapped breezeway cut through its base, and parking goes underground.
The site’s the hard part. It’s a 46,000-square-foot triangle at Central and Roosevelt whose depth changes sharply from one side to the other, which complicates truck access, fire lanes and floor plates. Intersection partner Jordan Taylor told AZ Big Media that “you can’t just build a box” there.
Why It Matters
Mid-size music venues are scarce in downtown Phoenix, and a 2,000-plus-capacity room booked 200 to 250 nights a year would fill a real gap between clubs and arenas. That part of the pitch holds up.
The financing deserves a harder look. Part of the equity is coming through a Regulation A offering that lets fans invest from $500, and the developer had put about $14 million into the project as of AZ Big Media’s earlier reporting. No general contractor or guaranteed price has been announced. A $124 million mixed-use tower on a tight urban lot with a below-grade garage isn’t cheap to carry, and crowd-sourced equity doesn’t replace a construction lender. Demolition is the easy milestone. The project’s credibility rides on what gets signed before Phase 2 starts.
Intersection has delivered about 15 hospitality and residential projects in Roosevelt Row over the past decade, so it knows the neighborhood. Taylor calls this one the capstone.
Related coverage & projects
Project Team & Details
| Developer | Intersection Development |
|---|
| Owner / Client | Intersection Development (under license from Atari) |
|---|
| Architect | räkkhaus |
|---|
| Status | Under Construction |
|---|
| Funding Source | Private |
|---|