Lynn has fought combined sewer overflows for decades, and the biggest single piece of the fix is buried beside a commuter rail line off Commercial Street. Methuen Construction’s $40.7 million West Lynn Sewer Separation Phase 3, a 96-million-gallon-per-day stormwater pump station, won Best Project in Water/Environment and an Excellence in Safety award in ENR’s 2026 East Best Projects on Nov. 5, 2026.
Phase 3 is part of a roughly $120 million program the Lynn Water and Sewer Commission wrapped up in April 2026. It traces back to a 2017 agreement with the U.S. EPA and the Justice Department to clean up the Saugus River and Lynn Harbor, with design starting in 2018. Across the program the commission separated about 260 acres of combined pipe and built more than 26,000 linear feet of new storm drain, CommonWealth Beacon reported. Clean Water State Revolving Fund loans paid for the work.
Project Scope
Stantec designed the station. Below grade it holds five submersible stormwater pumps, a dewatering pump, an inlet screening chamber, a wet well and a discharge valve vault. Above ground, a 1,856-square-foot masonry electrical building carries power, SCADA controls and standby generation. The point is to intercept storm flow and send it away from the wastewater treatment plant so the plant isn’t overwhelmed in heavy rain.
Discharge runs through roughly 1,000 feet of 54-inch HDPE force main inside a 66-inch steel casing, microtunneled along Commercial Street. Keller North America jet-grouted break-in and break-out blocks at the shafts, which bottomed out about 24 feet below the water table in Boston Blue Clay. With no room to lay out pipe, crews used a custom winch to pull fused sections through the casing. Methuen also preassembled large runs of 54-inch ductile iron process piping offsite.
Two field decisions stand out. Facing a high water table and supply chain delays, the team redesigned the wet well’s structural system to use less steel, which saved nearly $1 million, per ENR. And rather than bypass-pump a 48-inch storm drain during its temporary relocation, crews built a buried gravity bypass into an older parallel sewer across the street. That avoided pump noise, lane closures and the risk of flooding nearby homes.
Why It Matters
CSO programs are expensive, disruptive and slow, and plenty of older Massachusetts cities are still years from finishing theirs. Lynn separated East Lynn more than two decades ago and has now caught up on the west side, where the South Harbor waterfront is the city’s biggest redevelopment target. Clean water won’t guarantee that investment shows up. It does remove one of the main reasons it hasn’t.
Related coverage & projects
Project Team & Details
| Owner / Client | Lynn Water and Sewer Commission |
|---|
| Consultants | Stantec Consulting Services Inc. (Lead Design and Engineering) |
|---|
| General Contractor | Methuen Construction Co. |
|---|
| Major Subcontractors | Wayne J. Griffin Electric (Electrical) HB Fleming (Trade Partner) Keller North America (Ground Improvement) VR Concrete (Concrete) Super Excavators (Excavation) VARI-TECH (Trade Partner) Brighter Horizons (Environmental) Robert Irvine Co. (Trade Partner) CAM HVAC & Construction (HVAC) Empire Masonry (Masonry) Folan Waterproofing (Waterproofing) |
|---|
| Status | Completed |
|---|
| Funding Source | Public (State) |
|---|