Enfield hasn’t had a passenger train stop since October 1986. That changes in 2030. The Connecticut Department of Transportation broke ground Oct. 28, 2026, on the $125.3 million Enfield train station, a Hartford Line rail project in the Thompsonville neighborhood that closes a roughly 15-mile gap between Springfield Union Station and Windsor Locks.
The old stop closed after ridership fell to about five passengers a day. The Hartford Line is a different animal. CTDOT says it carried close to 600,000 riders last year, above pre-pandemic levels, and the state projects nearly 130,000 annual trips at Enfield by 2031.
Project Scope
The station itself is modest: a single 350-foot high-level platform on the east side of the track, a mostly enclosed waiting area, canopies, wind screens and an electric snow-melting system for the platform, ramps and stairs. There’s parking for about 80 cars, with EV chargers serving roughly 15 spaces, plus a bus bay sized for two full-size buses connecting to the town’s Magic Carpet service.
Most of the money goes into the railroad and the street. Crews will replace the railroad bridge over Main Street and lower the roadway to gain clearance underneath, then add sidewalks, streetscape work and pedestrian links into the neighborhood. About 4,400 feet of track gets realigned, along with signal, communications, drainage and utility upgrades. A new gauntlet track will let oversized freight loads clear the high platform, which keeps freight moving through the station area.
CTDOT opened bids July 29, 2026, on Contract 0320-0017, the Enfield station and track improvements package. Manafort Brothers Inc. was low at about $61.8 million, ahead of Rizzo Corp., Railroad Construction Co. and Walsh Construction. The bid tab carries 1,398 calendar days of contract time. Funding splits roughly 85% state and 15% federal, with money from the Federal Railroad Administration, the Federal Transit Administration and HUD.
Why It Matters
The scope has grown a lot. Early concepts priced an Enfield stop at $6 million to $9.5 million, and a 2023 plan pegged it at $45 million. The jump to $125 million reflects what it really takes to put a high-level platform on a live single-track freight and passenger corridor: a new bridge, realigned track and a gauntlet so freight shippers don’t lose clearance.
It’s also a housing play. The site sits inside the Bigelow-Hartford Carpet Mills Historic District, and the town has pushed transit-oriented development in Thompsonville for two decades. With trains projected at 23 minutes to Hartford and 13 minutes to Springfield, the station gives developers a reason to build around the old mill buildings. Whether ridership hits the state’s 2031 forecast will depend on frequency as much as on the platform.
Related coverage & projects
Project Team & Details
| Owner / Client | Connecticut Department of Transportation (CTDOT) |
|---|
| General Contractor | Manafort Brothers Inc. (apparent low bidder, CTDOT Contract 0320-0017) |
|---|
| Status | Under Construction |
|---|
| Delivery Method | Design-Bid-Build |
|---|
| Funding Source | Mixed |
|---|