Fort Worth’s commuter rail line is finally heading south. Trinity Metro broke ground on Oct. 29, 2026, on the $270 million TEXRail extension, a 2.1-mile addition that carries the 27.2-mile line past downtown’s T&P Station and into the Near Southside and Medical District. The ceremony took place at the future station site beside Baylor Scott & White All Saints Medical Center, and the agency expects trains to reach it in mid-2030.
It’s a short extension with a big catchment. Officials say the new stop puts about 50,000 jobs within reach of a line that already runs to Grapevine, North Richland Hills and DFW Airport’s Terminal B.
Project Scope
The work centers on one new station, Near Southside/Medical District, on 1.76 acres at Luther Lane and Mistletoe Drive. Baylor Scott & White Health donated the land, and a 35-year ground lease gives Trinity Metro the property rights it needs for access and improvements. Mass Transit reports that AECOM is building the project.
The trackwork is the more interesting part. Rather than buy a new corridor, Trinity Metro is paying Fort Worth & Western Railroad $6.1 million for perpetual easements on part of the short line’s existing freight corridor. A separate passenger track will run from the T&P Station, and a quiet zone will be set up along the route. The agency is also covering up to $363,825 for the railroad’s engineering and legal review and will carry a $200 million railroad liability policy once service starts.
Early agreements approved on Oct. 20 show what the prep work looks like: a 42-month owner-controlled insurance program costing just under $7.1 million, roughly $1 million to move an Oncor transmission pole near Mistletoe Drive, up to $1.6 million to bury overhead distribution lines, and about $111,000 for a small parcel at 800 12th Ave. needed for grading.
Why It Matters
Money for this one came from a lot of pockets. The funding stack includes federal CMAQ, STBG, BUILD and CRRSAA dollars, a $25 million U.S. DOT grant, Regional Transportation Council support and savings left over when the original TEXRail line came in under budget. The FTA put $499 million into the first build, which opened in 2019, and regional officials kept the leftover federal money in North Texas.
Ridership gives the case some weight. TEXRail logged 1,006,835 rides in fiscal 2026, up 15.5% from the prior year, with on-time performance of 98.84%. Reaching a hospital district, not just an airport, changes who the line serves. Patients, shift workers and students don’t keep airport hours.
Sharing a freight right-of-way also keeps costs down and the schedule tight, though it ties passenger operations to a host railroad’s corridor for decades. Officials already talk about pushing farther south toward TCU and Tarleton State’s Fort Worth campus. That extension isn’t funded yet.
Related coverage & projects
Project Team & Details
| Owner / Client | Trinity Metro (Fort Worth Transportation Authority) |
|---|
| Consultants | Higginbotham (Owner-Controlled Insurance Program) |
|---|
| General Contractor | AECOM |
|---|
| Status | Under Construction |
|---|
| Funding Source | Mixed |
|---|