Project Jupiter has its first frame. A Clayco and Kiewit New Mexico Co. joint venture placed the final structural beam on the 855,000-square-foot first building at the Project Jupiter data center campus in Santa Teresa, N.M., with Clayco announcing the topping out on Oct. 22, 2026. Ground broke in October 2025, so the steel took about a year.
STACK Infrastructure and BorderPlex Digital Assets are developing the campus. Oracle Cloud Infrastructure has leased it under an 18-year agreement, and OpenAI is the primary client. Doña Ana County approved up to $165 billion in industrial revenue bonds for the project in September 2025, though that’s a 30-year investment ceiling, not a construction budget.
Project Scope
The campus covers about 1,400 acres near the Mexican border, and it’s planned for four data center buildings. Phase 1 takes in roughly 400 acres and is targeted for the third quarter of 2028. Clayco says the job’s more than 25% complete, and around 4,400 workers have logged more than 3.7 million labor hours.
Power is the hard part. The original design leaned on gas turbines and diesel generators, but the team switched to an on-site microgrid built on Bloom Energy fuel cells, which cuts nitrogen oxide emissions by about 92%. Those fuel cells still need natural gas, though, and the proposed Green Chile pipeline has been rejected twice by the state land office. An air permit hearing is set for December.
Cooling’s closed loop and non-evaporative. The four systems get a one-time fill of non-potable well water bought from an existing water-rights holder, and no public drinking water goes to cooling or power generation. Oracle has also committed $50 million to Doña Ana County water system repairs.
Local trades are getting real work. Oracle says the project had awarded more than $994 million in contracts to 30 New Mexico firms as of Sept. 30, covering HVAC, insulation, plumbing, electrical and equipment rental, and 1,846 union members have worked on site.
Why It Matters
Clayco and Kiewit have shown they can stand up a frame this size in a year. That isn’t the constraint anymore. The constraint is firm power, and Jupiter is a live test of whether a fuel-cell microgrid can carry a gigawatt-class campus when the gas line feeding it is still in permitting.
Oracle has already sent a force majeure notice to the Blue Owl unit developing the site, which protects it if power slips, while saying the project remains on schedule. Contractors bidding the next wave of AI campuses should read that clause closely. Full build-out could draw up to 2.5 GW.
Related coverage & projects
Project Team & Details
| Developer | STACK Infrastructure; BorderPlex Digital Assets |
|---|
| Owner / Client | STACK Infrastructure and BorderPlex Digital Assets |
|---|
| Consultants | Bloom Energy (Fuel Cell Microgrid Supplier) |
|---|
| General Contractor | Clayco / Kiewit New Mexico Co. (Joint Venture) |
|---|
| Major Subcontractors | JB Henderson (Mechanical) |
|---|
| Status | Topped Out |
|---|
| Funding Source | Private |
|---|