Before anyone drove a pile at Bellefield, crews had to sweep for bombs. The 3,080-acre site outside Mojave, Calif., used to be a military munitions depot and bomb testing area, and it’s now the first phase of what AES says will be the largest solar-plus-storage facility in the U.S. ENR named Bellefield Solar Project 1 a Best Project in the Energy/Industrial category of its 2026 West Best Projects awards on Oct. 26, 2026.
AES Clean Energy owns it, and Primoris Renewable Energy built it with Primoris’ ARB Industrial and Primoris Electric units. Westwood Professional Services led design and Clark Bros. Inc. was civil contractor. AES announced the 1,000-MW first phase complete in June 2025, under a 15-year contract with Amazon.
Project Scope
Phase 1 installed 641 MWdc of solar (AES counts it as 500 MW) paired with 500 MW of four-hour battery storage. That took more than 1,187,000 Canadian Solar 540-watt modules and 160 Sungrow inverters. A dedicated 14-mile transmission line runs to Southern California Edison’s Windhub Substation, and a matching second phase is under construction, with AES targeting completion in 2026.
Tetra Tech handled unexploded ordnance, investigating and clearing ahead of every ground-disturbing activity, and every worker on site was trained to recognize what ordnance looked like. Dust was the other inherited problem. High winds over sandy, clay-like soil would’ve turned a cleared site into a dust bowl, so Primoris and Clark Bros. used a roll-and-crush method, flattening existing vegetation and working it into the soil instead of grading it off. The team puts the cut in fugitive dust at about 70%, with water, hydro-mulch and stabilizers covering the rest.
Wind caused a quieter problem too. It could relax torque on module hardware after bolts were set. The fix was to shake the panels to simulate wind loading before the final torque check, so the reading that gets recorded is the one that holds. To land balance-of-site material before the end of 2024, receiving went from 15 deliveries a day to more than 40 inside two weeks, which meant building extra roads and laydown.
Why It Matters
Bellefield is a data center project as much as a power plant. Amazon is the buyer, and AES has framed the build as proof that solar and storage can be deployed fast enough to keep up with hyperscaler demand. More than 700 union workers built Phase 1, according to AES.
The construction lessons travel well. Old military land is cheap and flat, and there’s a lot of it in the desert Southwest. Bellefield shows the UXO, dust and logistics bill that comes with it, and that a crew can pay it on a gigawatt schedule.
Related coverage & projects
Project Team & Details
| Developer | AES Clean Energy |
|---|
| Owner / Client | AES Clean Energy |
|---|
| Consultants | Westwood Professional Services (Lead Design) Tetra Tech (UXO Investigation and Clearance) Stantec (Consultant) |
|---|
| General Contractor | Primoris Renewable Energy (with ARB Industrial and Primoris Electric) |
|---|
| Major Subcontractors | Clark Bros. Inc. (Civil) Hampton Tedder Electric (Electrical) Merit SI (Trade Partner) EnviroPlus (Trade Partner) Aggreko (Temporary Power) RESA Power (Electrical Testing) Badger Daylighting (Hydro Excavation) Ericsson Grant (Trade Partner) Nexus 3D (Trade Partner) Diversified Project Services (Trade Partner) CAL-Storm (Stormwater) |
|---|
| Status | Completed |
|---|
| Funding Source | Private |
|---|