Avia Labs didn’t have room for a laydown yard, a setback or a tall crane plan. Longfellow Real Estate Partners’ six-story life science building sits on a former self-storage lot in Millbrae, Calif., squeezed between an active BART line and the Millbrae Road overpass and less than half a mile off the end of San Francisco International Airport’s east-west runway, which capped its height. ENR named the $200 million project a Best Project in its 2026 West Best Projects awards on Oct. 26, 2026.
Level 10 Construction finished it on time and on budget in November 2025, per ENR. Flad Architects designed it. Longfellow broke ground in March 2023 and has billed it as California’s first all-electric life science building.
Project Scope
The building totals 315,000 square feet, split about evenly between lab and office, with two levels of underground parking. ENR puts the site at 2.7 acres with no setback on any side. Crane picks, deliveries and major installations were scheduled to the hour because there was nowhere to stage and a live rail line ran along one boundary.
The facade did a lot of the structural work. On the south and east elevations, Enclos and the team set interlocking glass fiber reinforced concrete mega panels, fabricated off site and installed as units. They’re lighter than a conventional wall assembly, so they took load out of the frame and the foundations, and prefabrication cut both install time and the need for laydown. The west side, facing the rail station, gets curtain wall with acoustically glazed units to keep train noise out while pulling daylight deep into the floor plates. Vibration and noise control carry through the structure because tenants will run sensitive instruments.
The lab is all-electric with rooftop photovoltaics and no on-site fossil fuel combustion. A life-cycle analysis of the concrete, rebar, facade and cladding steered material choices toward lower embodied carbon, and the project is targeting LEED Gold. JLL arranged a $310 million construction loan from Otera Capital in 2023.
Why It Matters
Peninsula lab space has been a hard market since the 2023 slowdown, and a lot of planned buildings never left the drawing board. Avia Labs got built, and it got built next to the only Bay Area station where BART and Caltrain meet. That’s the bet: transit access and an all-electric spec will rent when generic suburban lab space won’t.
For builders, it’s a case study in tight-site logistics. A 315,000-square-foot building on 2.7 acres, under an airport height limit and beside a live rail line, isn’t a normal job, and the precast panel strategy is the kind of decision that only pays when the site leaves no other choice.
Related coverage & projects
Project Team & Details
| Developer | Longfellow Real Estate Partners |
|---|
| Owner / Client | Longfellow Real Estate Partners |
|---|
| Architect | Flad Architects |
|---|
| Consultants | BKF Engineers (Civil Engineering) Salas O'Brien (Structural Engineering) Meyers+ Engineers (Mechanical Engineering) Scape (Landscape Architecture) Heintges (Building Envelope) |
|---|
| General Contractor | Level 10 Construction |
|---|
| Major Subcontractors | Largo Concrete (Concrete) Enclos (Facade) Malcolm Drilling (Foundations) Jos J Albanese (Trade Partner) PSG Rebar (Rebar) Willis Construction (Trade Partner) CSI Electric (Electrical) Silicon Valley Mechanical (Mechanical) Lee's Imperial Welding (Welding) TK Elevator (Elevators) |
|---|
| Status | Completed |
|---|
| Sustainability Certification | LEED Gold (targeted) |
|---|
| Funding Source | Private |
|---|