Denver Summit FC broke ground on its permanent stadium at Santa Fe Yards on Oct. 1, 2026, nine months after hiring Mortenson as construction manager. The NWSL expansion club’s women’s soccer stadium sits at South Broadway and Interstate 25, south of downtown Denver, and Populous is the architect.
The ceremony also confirmed what a lot of fans had suspected. The stadium won’t be ready for the start of the 2028 season. Target completion is now the end of 2028, and the club expects to play most of its 2028 home schedule at Centennial Stadium, its 12,000-seat temporary venue at the CommonSpirit Performance Center.
Project Scope
The stadium is the anchor of a 14-acre, transit-oriented sports and entertainment district the team bought in March 2026. The club’s groundbreaking release puts capacity at 12,500 fixed seats plus safe-standing zones, for 13,000 total. That’s smaller than the roughly 14,500 seats reported when Mortenson was hired in January.
The design leans on open-air social spaces, expanded terraces, seating tight to the pitch and local food and beverage. Populous designed the canopy. Denver-based CAA ICON handles project management, and Gratacon is also on the team.
Construction Dive put the job at $225 million in January. The club didn’t repeat a figure at groundbreaking.
Why It Matters
Purpose-built women’s soccer stadiums are still rare. Kansas City’s CPKC Stadium was first, and Denver’s would be the second. It’s a test of whether the format works at 13,000 seats in a big-league market without an anchor tenant from another sport.
The public money is real but limited. Denver City Council committed $50 million in late 2025 after the club threatened to walk away from the deal, which puts the city on the hook for a minority share of a privately led project.
For Mortenson, which has been piling up sports work, it’s another venue on a growing list. The bigger questions are about the district. A 14-acre site at a major interchange has room for a lot more than a stadium, and none of that later phase has a builder, a budget or a schedule yet. The capacity cut and the schedule slip deserve attention. Neither is unusual for a stadium in design development, but both moved in the same direction.
Related coverage & projects
Project Team & Details
| Owner / Client | Denver Summit FC |
|---|
| Architect | Populous |
|---|
| Consultants | CAA ICON (Project Management) Gratacon (Associated Partner) |
|---|
| General Contractor | Mortenson |
|---|
| Status | Under Construction |
|---|
| Delivery Method | CMAR |
|---|
| Funding Source | Mixed |
|---|