The Dolphin Square refurbishment in Pimlico is working through 1,234 apartments in 13 brick blocks beside the Thames, on an estate that stays occupied while the work goes on. Galliford Try is now on phase two, covering six of the estate’s houses and 542 homes, for owner AXA IM Alts.
The estate went up between 1935 and 1937. Its services have been patched ever since.
Project Scope
GRID Architects leads design, with Heyne Tillett Steel as structural engineer and Cundall on M&E and sustainability, according to New London Architecture’s project record. DP9 is planning consultant, Sally Prothero the landscape architect, Affinity Fire the fire engineer and DesignPlusLight the lighting designer. Galliford Try has been main contractor on both phases.
Phase one refurbished roughly 360 apartments in three houses, mostly studios and one-beds, along with a new reception, a gym and restored squash courts. Phase two, awarded in March 2025, takes on Keyes, Hood, Collingwood, Frobisher, Grenville and Drake houses. The contractor’s scope includes structural alterations, layout changes, facade repairs, new roof systems carrying air source heat pumps and photovoltaic panels, and 2,846 replacement sash windows. RIBA Journal counted about 6,000 single-glazed windows across the estate.
Targets for phase two are BREEAM Excellent and WELL Platinum. RIBA Journal reported phase two due in 2027 and the final residential phase in 2028. Galliford Try hasn’t disclosed its contract value.
Why It Matters
This is a decarbonization job dressed as a rental upgrade. The estate ran on communal gas heating. AXA says the retrofit is designed to cut carbon emissions 95 percent and on-site energy demand 80 percent, and to end fossil fuel use on site. Bisnow reported in July 2025 that phase one installed 40 air source heat pumps and 400 solar panels, and that occupancy in the finished blocks climbed from 50 percent to 98 percent.
The buildings themselves aren’t listed, though the central garden is Grade II and the estate sits in a conservation area. That constraint explains the sashes: nearly 3,000 like-for-like window replacements in one phase isn’t the cheap route. GRID’s director told RIBA Journal that from a sustainability standpoint the estate “was a nightmare.”
The money is patient. Bisnow put AXA’s purchase at about £800 million and the refurbishment above £250 million, for a total past £1 billion. Institutional capital doesn’t often spend that on 90-year-old flats it can’t knock down.
If the rents hold, expect other owners of interwar mansion blocks to copy the method. If they don’t, AXA owns a very well-insulated lesson.
Project Team & Details
| Developer | AXA IM Alts |
|---|
| Owner / Client | AXA IM Alts |
|---|
| Architect | GRID Architects |
|---|
| Consultants | Heyne Tillett Steel (Structural) Cundall (M&E, Sustainability) DP9 (Planning) Sally Prothero (Landscape) Affinity Fire (Fire) DesignPlusLight (Lighting) |
|---|
| General Contractor | Galliford Try |
|---|
| Status | Under Construction |
|---|
| Sustainability Certification | BREEAM Excellent, WELL Platinum (phase two targets) |
|---|
| Funding Source | Institutional |
|---|