England hasn’t opened a major new reservoir in more than 30 years, and Havant Thicket is taking its time ending that streak. Portsmouth Water appointed Clancy on Oct. 22, 2026, to a £26.84 million contract for a new pumping station and an 8.5-kilometre treated-water pipeline, the next big package on a Hampshire scheme whose opening has slipped to 2034 and whose estimated cost has climbed past £800 million.
The reservoir sits on 160 hectares of grassland north of Havant that Portsmouth Water has owned since the mid-1960s. It’ll hold about 8.7 billion litres.
Project Scope
The basin itself runs about 1.7 kilometres east to west, with a 5.2-kilometre perimeter and a deepest point of 21 metres, built over London Clay. Future Water MJJV, a Mackley and Jones Bros joint venture, holds the £167 million main reservoir works contract awarded in 2023. Ward & Burke Construction has the £41 million inlet pipeline, a largely tunnelled two-mile line that’ll fill the reservoir in winter with surplus flow from the Bedhampton Springs, water that otherwise runs to the sea.
Clancy’s package handles the outbound side. Crews start in December on a pumping station at Farlington Water Treatment Works and the 8.5-kilometre pipe to a treated-water storage site north of Portchester. The line is sized for up to 32.4 million litres a day, and the contract is due to wrap up in early 2030.
Average supply from the reservoir is planned at 21 million litres a day. Planning permission came in 2021, and upfront finance comes from Ancala and a bank consortium, with Southern Water customers repaying it through their bills over many years.
Why It Matters
The reservoir exists to take pressure off two chalk streams. Southern Water draws heavily on the Rivers Test and Itchen, and Havant Thicket’s stored water is meant to let it cut those abstractions. With drought orders becoming routine in southern England, that’s a real resilience gain, not a press-release one.
The schedule is the cautionary tale. The original completion target was 2029. By February 2026 that had moved to 2031 at about £340 million, and by September the estimate had more than doubled to £800 million with a 2034 opening. Local reporting has tied the jump to a water recycling project linked to the reservoir.
For contractors, Havant Thicket is a preview of what England’s planned new reservoirs will look like: long, phased programs split into separately let civils, tunnelling and pipeline packages, with financing and regulators shaping the pace as much as the ground does.
Project Team & Details
| Owner / Client | Portsmouth Water |
|---|
| General Contractor | Future Water MJJV (Mackley / Jones Bros JV) - Main Reservoir Works |
|---|
| Major Subcontractors | Ward & Burke Construction (Inlet Pipeline) Clancy (Farlington Pumping Station and Outbound Pipeline) |
|---|
| Status | Under Construction |
|---|
| Funding Source | Private |
|---|