The Citi Tower redevelopment at 25 Canada Square opened to its first staff on September 21, 2026, closing out a three-year strip-and-rebuild of a 200-metre Canary Wharf office tower that Citi says cost $1.5 billion. The bank bought the building for £1.2 billion in 2019. It has now spent roughly that again making it the headquarters it wanted.
The budget history deserves a look. Trade press pegged the contract at about £300 million when Overbury won it in early 2022, with a 2025 finish.
Project Scope
Overbury, Morgan Sindall’s fit-out arm, served as main contractor on a scheme designed by WilkinsonEyre and known as Project Saturn. The Construction Index lists Buro Happold as engineer and Turner & Townsend as cost consultant. HDR says it provided MEP and structural engineering, vertical transportation, technology consultancy and energy assessments, and acted as commissioning manager alongside the contractor.
The tower dates to 2001 and was designed by Cesar Pelli & Associates. Work on site started in July 2023. Crews cut out sections of existing floor slab to form double- and triple-height atria and winter gardens, which the design stacks into “villages” around a mid-tower town square. New operable facade sections allow natural ventilation. HDR puts the building at 1.2 million square feet and says the lift count rises from 42 to 65, with fresh air supply going from 10 to 16 litres per second per person. Its MEP model ran to 6.5 million components.
Certification targets, per HDR, are BREEAM Excellent, LEED v4 Platinum and WELL Platinum, with the energy performance certificate moving from D to B. As many as 1,800 operatives worked on site. Citi says more than 10,000 construction workers passed through the job overall and that over 90 percent of materials came from Europe, mostly from U.K. suppliers.
Why It Matters
Citi chose to keep the frame. The original case rested on about 100,000 tonnes of embodied carbon saved against demolition and new build, a figure Construction Enquirer reported in 2022. That argument still holds. The cost argument is harder to make.
A tower job that grows from a reported £300 million to more than £1 billion isn’t a fit-out anymore. Cutting slabs, reworking facade and adding 23 lifts inside a standing high-rise is heavy structural work at new-build prices, and owners weighing retain-and-retrofit schemes elsewhere on the estate will read this one closely. Nobody outside the bank has seen the scope changes that drove the number, and Citi’s press release doesn’t name a single member of the project team.
About 10,000 Citi staff are due in the building once the move finishes. It runs in phases through the rest of 2026.
Related coverage & projects
Project Team & Details
| Developer | Citi |
|---|
| Owner / Client | Citi |
|---|
| Architect | WilkinsonEyre |
|---|
| Consultants | HDR (MEP, Structural, Vertical Transportation, Commissioning) Buro Happold (Engineer) Turner & Townsend (Cost Consultant) |
|---|
| General Contractor | Overbury (Morgan Sindall Group) |
|---|
| Status | Completed |
|---|
| Sustainability Certification | BREEAM Excellent, LEED v4 Platinum, WELL Platinum (targets, per HDR) |
|---|
| Funding Source | Private |
|---|