The seats are in. Regent Bank Amphitheater, the 12,500-seat concert venue VENU has been building in Broken Arrow’s Events Park, entered its final stretch of construction this week, with crews “tightening the bolts” ahead of a New Year’s Eve opening show, a VENU executive told KTUL on Nov. 17, 2026. Randy Rogers Band, Josh Abbott Band and Ed Morris are booked for the first night.
It’s later than planned. VENU had pointed to the 2026 touring season and, at one point, a second-quarter opening. The schedule slid this fall, and the Tulsa World reported Nov. 9 that opening day had been pushed back.
Project Scope
The venue sits on about 13 acres inside Events Park, roughly 15 minutes from Tulsa International Airport and downtown Tulsa. Upper and lower bowl seating is covered. Instead of a lawn, the design switched to fixed bench seating, wind walls and radiant heating so the building can book shows in cold months. There are more than 200 fire suites with gas fire pits, a Troy Aikman suite level, a pit area near the stage, stories-tall video screens, ceiling fans and hundreds of heaters. The bowl can also shrink to a 5,000-seat setup for smaller events. Behind the stage, an “Artist Compound” gives touring crews showers, laundry and a golf simulator.
Two Crossland companies split the work. Crossland Construction is construction manager for the venue itself. Crossland Heavy Contractors is construction manager for the City of Broken Arrow’s share: parking, turnpike access and road widening. The city has widened 101st Street and New Orleans Street, and worked with the Oklahoma Turnpike Authority on a new loop on-ramp, giving the site three ways in and four ways out. One piece is still waiting on railroad approval, the north end of a new 43rd Street connecting toward Highway 51.
Why It Matters
This is a public-private partnership in the real sense. The city supplied the site and the access roads, and VENU is paying for the building. The money side has been bumpy. Reported budgets have run from $75 million to $107 million in 2025 coverage, and Pollstar later put the price tag near $300 million. In August, VENU closed a $25 million secured convertible debenture to carry the job to completion, with a C-PACE loan expected to take that out.
The bet behind all of it is year-round operation. VENU argues a heated, suite-heavy building can run far more dates than a summer-only shed, and Broken Arrow is the test case before larger venues it’s developing in Texas. If the winter calendar fills, the extra cost of heat and enclosure pays off. If it doesn’t, owners elsewhere will notice fast.
Project Team & Details
| Developer | VENU Holding Corporation |
|---|
| Owner / Client | VENU Holding Corporation |
|---|
| General Contractor | Crossland Construction Company (Construction Manager, venue) |
|---|
| Major Subcontractors | Crossland Heavy Contractors (Construction Manager for City of Broken Arrow site infrastructure: parking, turnpike access, road widening) |
|---|
| Status | Under Construction |
|---|
| Funding Source | Public-Private Partnership (P3) |
|---|