Manchester, N.H., broke ground Nov. 17, 2026, on the new Beech Street Elementary School, a 111,059-square-foot K-4 building for 735 students that’s going up directly across the street from the school it replaces. Crews from construction manager Harvey Construction had already been working the site for months. The ceremony, with students on shovels, caught up to them.
Project Scope
SMMA designed the school as two three-story classroom wings set on the quieter side of the site, joined to a two-story public wing that faces Beech Street. The district’s list of program pieces reads like a reaction to the old building: right-sized classrooms with daylight and views, a learning commons shared by every grade, small-group rooms beside classrooms, dedicated offices for counselors, psychologists and intervention staff, calming rooms for general and special education students, and a gym and cafeteria that are finally separate rooms. The secure entry vestibule sits inside the main office so staff can see who’s coming in. There’s also a roof terrace with a pergola for outdoor teaching.
The site is tricky. It’s city park land, and a historic culvert runs under it, so SMMA’s engineers used deep foundations and a buffer zone to keep the structure off the culvert, with vibration monitors watching it during construction.
The district’s schedule calls for substantial completion in April 2028 and a September 2028 opening. After that, the current Beech Street school comes down and the land becomes athletic fields, a basketball court and play areas, so the neighborhood swaps one park parcel for another.
Why It Matters
The existing Beech Street school is a 68,896-square-foot building on 1.5 acres, and it enrolled 467 kids in 2024-25. The new one will take on students from Henry Wilson Elementary, which closed in June 2024, and the district has been running modular classrooms since August 2024 to bridge the gap. That’s a consolidation, not just a replacement.
It’s also the biggest single piece of Manchester’s $306 million Priority One facilities plan, which is why the slow start stung. The school board approved the concept in November 2023 with a hoped-for early 2027 finish. The schedule has since slid by well over a year.
What Manchester gets for the wait is a school sized for 735, built by a construction manager based one town over in Bedford. If the culvert behaves, the hard part is underground and nearly behind them.
Project Team & Details
| Owner / Client | Manchester School District |
|---|
| Architect | SMMA |
|---|
| Consultants | SMMA (Engineering, including Deep Foundation Design) |
|---|
| General Contractor | Harvey Construction |
|---|
| Status | Under Construction |
|---|
| Delivery Method | CMAR |
|---|
| Funding Source | Public (Municipal) |
|---|