Small jobs don’t usually make headlines. Taunton’s did. ENR’s 2026 East Best Projects judges named the Taunton Pump Station Improvements the region’s Best Small Project, a $2.7 million upgrade that rebuilt power and pumping at four wastewater pump stations in the southeastern Massachusetts city.
Walsh Construction Co. was the general contractor and submitted the entry. Veolia Water North America-Northeast served as lead design firm and owner’s representative, with Beta Group Inc. as civil engineer and SAR Engineering on electrical design.
Project Scope
The work was spread across four sites, and each had its own access, sequencing and utility problems. One station needed a much bigger systems upgrade than the others, on a cramped lot next to a two-lane road.
That’s where the job got interesting. Test pits turned up an existing communications conduit system sitting in the planned path of the new power ductbank. Rather than relocate more utilities, the team redrew the alignment with a diagonal crossing of the adjacent road. It cost time. To win it back, crews set a precast structure for the station’s 14-foot-diameter wet well and used a slide-rail support of excavation system to place the wet well and an 11-by-9-foot valve vault inside a tight footprint, close to the road and existing buried lines.
At a second station, wiring that was supposed to be reused turned out to be damaged beyond repair. The team mobilized bypass pumping to keep sewage moving while the extra electrical work got done. Carefully sequenced bypass kept the existing system running throughout the project.
The subcontractor bench was deep for a job this size. E.W. Audet & Sons, Capital City Construction Management Services, Keltic Painting, R.E. Erickson Co., Pacella Enterprises, Strategic Environmental Services, Mass Crane & Hoist Service, Mersino Dewatering and Carlsen Systems all worked on it.
Why It Matters
Pump stations are where a lot of New England’s sewer risk actually lives. Taunton sits along the Taunton River, and BETA’s earlier work for the city on stations such as Dean Street was driven by aging pumps and wet-weather flows that overwhelm capacity. Old gear fails at the worst moment, usually in a storm.
What stands out here is the schedule math. Despite several owner-approved changes, the team stayed inside its original contingency, and early procurement let it fabricate and install the new gear and equipment seven months ahead of schedule. With electrical equipment lead times still stretched, ordering early is often the whole game on a small municipal job, and this one shows it.
Related coverage & projects
Project Team & Details
| Consultants | Veolia Water North America-Northeast (Lead Design Firm and Owner's Representative) Beta Group Inc. (Civil Engineer) SAR Engineering (Electrical Engineer) |
|---|
| General Contractor | Walsh Construction Co. |
|---|
| Major Subcontractors | E.W. Audet & Sons Inc. Capital City Construction Management Services Inc. Keltic Painting (Painting) R.E. Erickson Co. Pacella Enterprises Inc. Strategic Environmental Services Mass Crane & Hoist Service Inc. Mersino Dewatering (Dewatering) Carlsen Systems |
|---|
| Status | Completed |
|---|
| Funding Source | Public (Municipal) |
|---|