The Happy Canyon Road bridge over I-25 is about to get a twin, and then a replacement. Castle Pines, Douglas County and the Colorado Department of Transportation broke ground Nov. 13, 2026, on a $39.3 million rebuild of the Happy Canyon interchange that converts it to a diverging diamond, with completion expected in early 2029.
Kraemer North America is the contractor, brought in through a construction manager/general contractor process. Castle Pines runs the project as owner and project manager.
Project Scope
Crews will build a new three-lane bridge just north of the existing structure while traffic keeps using the old one, then replace the original bridge. The job also rebuilds the I-25 on- and off-ramps and upgrades signals and intersections across the interchange. Phase 1, running from fall 2026 into summer 2027, covers the new bridge and the north ramps. Girder setting will need full overnight I-25 closures with traffic detoured up the ramps.
To get room in the median for bridge foundations, crews will narrow and shift I-25 lanes to the outside while keeping four lanes each way for most of the job. The speed limit in the work zone drops to 65 mph. The first lane realignment closures run nightly Nov. 16 through Nov. 19.
The funding stack has three pieces: $15.3 million from Douglas County’s voter-approved Fund 235, paid in two installments tied to the city’s contract awards, $12.8 million from the city and associated developments, and an anticipated $11.2 million from CDOT and its Statewide Bridge and Tunnel Enterprise, of which $1 million is held for future maintenance.
Why It Matters
The diverging diamond won on cost and capacity. Wilson & Company’s 2024 alternatives analysis looked at roundabouts, which it found would fail under 2050 volumes, and a single-point urban interchange, which handled the traffic but came in about 21% more expensive. The DDI crosses traffic to the left side of Happy Canyon Road so left turns onto I-25 don’t cut across oncoming lanes, and it needs a two-phase signal instead of four or six.
Growth is forcing the issue. Approvals for nearby developments, including The Canyons, were contingent on fixing this interchange, and that development is chipping in on construction. The CM/GC choice makes sense too. A contractor at the table during design can sequence a bridge build beside a live interstate before the price is locked, and that’s where change orders usually come from.
Related coverage & projects
Project Team & Details
| Owner / Client | City of Castle Pines |
|---|
| Consultants | Wilson & Company (Interchange Alternatives Analysis / Traffic Study) |
|---|
| General Contractor | Kraemer North America |
|---|
| Status | Under Construction |
|---|
| Delivery Method | CMAR |
|---|
| Funding Source | Mixed |
|---|