Gilbert is rebuilding a water plant that was poorly built the first time. The town said Nov. 4, 2026, that its North Water Treatment Plant reconstruction has reached 75% completion, on schedule and inside the approved budget, with the new treatment process due to start up in spring 2027 and final completion expected in winter 2028.
The plant at Higley and Guadalupe roads dates to the mid-1990s and treats Salt and Verde river water delivered through Salt River Project’s Eastern Canal. When SRP dried up its canals for maintenance in 2018, town staff finally got a look at buried and submerged structures and found at least $70 million in structural repairs, much of it traced to construction quality, including misplaced and undersized rebar. Rather than patch it, Gilbert chose to rebuild and expand.
Project Scope
A Sundt/PCL joint venture is building the job as construction manager at risk under phased guaranteed maximum price packages. Kennedy Jenks holds a roughly $15 million program and construction management contract. Before design, Gilbert ran a year-long pilot plant with Corona Environmental Consulting and Sundt to test treatment trains against highly variable river water.
The work runs in five phases. The first replaced solar drying beds with belt filter presses and gravity thickeners, freeing room for new process buildings. The second built a new raw water inlet off the SRP canal during a rare canal shutdown, using a temporary cofferdam. Later phases add a filter complex, chemical facility, operations center, pump stations, a granular activated carbon facility, on-site sodium hypochlorite generation and a wash water recovery basin. The last package adds two pre-sedimentation basins and a sludge pump station, then demolishes or repurposes the old plant. Capacity rises from 45 mgd to 60 mgd.
Why It Matters
This is the largest capital project in Gilbert’s history, and the price shows why owners shouldn’t treat water plants as commodities. The town’s estimate climbed from $457 million to $677 million ahead of its rate vote, PCL cites a $536 million construction value, and local reporting put the overall project at $692 million in October 2025. Water rates are the main funding source, and the town proposed a 134% rate increase phased in over three years to cover it.
The town’s own explanation is pointed. Staff said the original plant went to the low bidder before Arizona allowed qualifications-based selection in 2000. The rebuild uses the opposite approach, with a CMAR team led in part by Sundt, which has built Gilbert water plants since 2005. When it’s done, the North plant will supply more than 70% of the town’s water. The final GMP packages still have to go to the Town Council within the next year, so the budget isn’t closed yet.
Related coverage & projects
Project Team & Details
| Owner / Client | Town of Gilbert |
|---|
| Consultants | Kennedy Jenks (Program/Construction Management) Corona Environmental Consulting (Pilot Testing) |
|---|
| General Contractor | Sundt/PCL Joint Venture (CMAR) |
|---|
| Status | Under Construction |
|---|
| Delivery Method | CMAR |
|---|
| Funding Source | Public (Municipal) |
|---|