It took a decade, a barge strike and a windstorm, but Philadelphia’s Schuylkill Crossing swing bridge opens to walkers and cyclists on Nov. 13, 2026. The 1,000-foot trail segment crosses the Schuylkill River just south of the Grays Ferry Avenue Bridge, tying Grays Ferry Crescent on the east bank to Bartram’s Mile and Bartram’s Garden on the west.
A.P. Construction built it for the City of Philadelphia’s Department of Streets, working with the Schuylkill River Development Corporation. Ammann & Whitney, since folded into WSP, did the feasibility study and final design.
Project Scope
This is a real movable bridge, not a fixed span dressed up as one. A new steel center truss pivots on the rehabilitated stone pier left from the 1901 Philadelphia, Wilmington and Baltimore Railroad swing bridge, which Conrail took out of service decades ago and the city demolished down to its substructure in 2018. The turning mechanism is built into that historic pier, and a new fender system protects it. Both approach spans were rehabilitated to carry the trail.
Crews set the six truss segments in July 2025, then joined them, poured a lightweight concrete deck pumped from trucks parked on the Grays Ferry Avenue Bridge, and added stainless mesh railing inserts and accent lighting. Fall 2026 went to balancing and testing the electrical and mechanical systems. When a tall vessel needs through, gates close, a bell rings and an operator swings the span from a control house.
The balancing work paid off. With about 60,000 pounds of mechanical steel on the center pivot, the truss could be pushed by hand, a city construction engineer told NBC10.
Why It Matters
The original idea, floated in 2012, was to jack the old truss up roughly 33 feet so boats could pass under it. The Coast Guard said no because tugs serving the upstream power plant wouldn’t clear. So the team kept the old piers and built a lighter span that crosses at grade and swings.
The schedule is the cautionary part. Federal TIGER money landed in late 2015, when the job was pegged at about $13 million with a 2017 finish. The construction contract came in at $15 million, and the city says final costs are still being settled after the pandemic, material price spikes, truss redesign, a 2020 barge collision and wind damage to parts fabricated in Coatesville. Movable bridges are unforgiving that way.
What riders get is a continuous off-road route from Bartram’s Garden north through Center City, and the last missing link in roughly 70 miles of Schuylkill River Trail toward Reading.
Related coverage & projects
Project Team & Details
| Developer | Schuylkill River Development Corporation |
|---|
| Owner / Client | City of Philadelphia, Department of Streets |
|---|
| Consultants | Ammann & Whitney, now WSP (Feasibility Study and Final Design) |
|---|
| General Contractor | A.P. Construction |
|---|
| Status | Completed |
|---|
| Delivery Method | Design-Bid-Build |
|---|
| Funding Source | Mixed |
|---|