Kansas City spent six decades burning its sludge. The Blue River Wastewater Treatment Plant biosolids facility ends that. Black & Veatch and Goodwin Brothers Construction tore out the plant’s 1960s-era incinerators and built a thermal hydrolysis and anaerobic digestion complex on the old incineration building’s foundation, and ENR named the job a Best Project in the Water/Environment category of its 2026 Midwest Best Projects on Nov. 9, 2026.
Blue River is the city’s largest plant. It’s rated for 120 million gallons a day and also takes solids from two other Kansas City Water treatment plants, so it couldn’t go offline for a single day of the rebuild.
Project Scope
The core of the job is a thermal hydrolysis process (THP) system, which ENR calls the Midwest’s first large one. THP cooks sludge under high pressure and temperature before it goes to the digesters. That sterilizes it, breaks it down and boosts biogas yield, and it let the city push more solids through digesters it already owned instead of building new ones. The facility now produces up to 94 dry tons a day of Class A biosolids for farm and residential land application.
The team reused what it could. Existing digesters, holding tanks, corridors and foundations stayed in service or were upgraded. Old dissolved air flotation tanks were converted into a sidestream deammonification system that removes about 80% of the nitrogen in the plant’s return flows, according to Black & Veatch. A flexible membrane cover on an existing tank holds 118,000 cubic feet of biogas, roughly a three-hour buffer. What was planned as three separate buildings became one.
Black & Veatch designed it and Goodwin Brothers built it under a fixed-price design-build contract with the Kansas City Water Services Department. The THP equipment was negotiated and ordered before COVID-era supply chain delays hit. Commissioning came in steps so the digesters’ biology never crashed. Funding, about $150 million per the designer, came from municipal revenue bonds, a WIFIA loan and state revolving fund loans.
Why It Matters
Biosolids incinerators installed decades ago are wearing out across the country just as Class A land application standards tighten. Blue River is a working example of replacing one inside a live plant with no spare land, and that’s the constraint most older utilities actually face.
The energy story is still half done. Biogas is being captured now, but a separate project is treating it for injection into the natural gas system, so the fossil-fuel offset isn’t fully booked yet. The project also won the AAEES 2026 Grand Prize in Design and has been submitted for Envision Silver verification. The award judges liked it. The real test is whether those 94 tons a day find steady buyers.
Related coverage & projects
Project Team & Details
| Owner / Client | City of Kansas City, Mo. (Kansas City Water Services Department) |
|---|
| Consultants | Black & Veatch (Lead Design Firm / Design-Builder Designer) |
|---|
| General Contractor | Goodwin Brothers Construction (Design-Build Contractor) |
|---|
| Status | Completed |
|---|
| Delivery Method | Design-Build |
|---|
| Sustainability Certification | Envision Silver (submitted for verification) |
|---|
| Funding Source | Public (Municipal) |
|---|