The new Mississippi River bridge at Lansing, Iowa, opens to traffic Nov. 6, 2026, roughly six months ahead of its original spring 2027 target. That’s a reversal for a $140 million job that, in mid-2025, was losing weeks at a time to an old bridge that wouldn’t hold still.
The 1,724-foot steel through-truss carries Iowa 9 and Wisconsin 82 between Lansing and rural Crawford County, Wis. It’s the only river crossing for about 30 miles, so the free car ferry the two DOTs ran during the closure carried almost 131,000 vehicles through August.
Project Scope
Kraemer North America, based in Plain, Wis., is the prime contractor on the design-bid-build job, which started in October 2023. The Iowa Department of Transportation leads it with WisDOT as partner, and federal funds cover about 80% of the cost.
The new bridge’s truss runs 1,352 feet and was shaped to echo the 1931 cantilever truss it replaces, at the community’s request. Everything else got bigger. The main channel span grew to 750 feet, the roadway went from 21 to 40 feet wide, and foundations go about 150 feet down, compared with roughly 55 feet for the old piers, which sat on timber piles.
Burns & McDonnell handled the environmental assessment and early bridge engineering, including an alignment that cut the structure length and avoided the most sensitive wetlands in the Upper Mississippi refuge. Foth Infrastructure & Environment, working with Parsons, carried the design into Iowa DOT’s first full-scale digital delivery. The team modeled all 5,450 tons of steel, 4,600 connection plates and nearly 180,000 bolts to LOD 400, and Bentley credits the model with about $3.2 million in savings. Des Moines firm Confluence led aesthetic treatments for piers, abutments and retaining walls.
The hard part came from next door. The old bridge stood about 75 feet away, and pile driving for the new one repeatedly pushed its movement past safety limits. By June 2025, Kraemer estimated the stoppages had added more than 100 days. The DOTs then closed the 1931 span in October 2025 and blew it up on Dec. 19.
Why It Matters
Removing the old bridge early cost local drivers a year of ferry rides and long detours through Prairie du Chien. It also gave the contractor an open river and a clean critical path, which is how a project that had been running behind ends up finishing early.
For owners of other aging river crossings, Lansing makes the trade-off clear. Building tight against a fragile structure saves right-of-way and environmental impacts, but it puts the old bridge’s condition on the new bridge’s schedule. Here, giving up the old crossing sooner got the new one open faster.
Related coverage & projects
Project Team & Details
| Owner / Client | Iowa Department of Transportation and Wisconsin Department of Transportation |
|---|
| Consultants | Burns & McDonnell (Environmental and Bridge Engineering) Foth Infrastructure & Environment (Bridge Design and Digital Delivery) Parsons (Bridge Design) Confluence (Aesthetic Design) |
|---|
| General Contractor | Kraemer North America |
|---|
| Status | Under Construction |
|---|
| Delivery Method | Design-Bid-Build |
|---|
| Funding Source | Public (Federal) |
|---|