The Adeline affordable housing tower is the biggest swing Ann Arbor has taken at its housing shortage in years. Related Midwest and the Ann Arbor Housing Commission broke ground in late September 2026 on the 20-story, 330-unit building at 350 S. Fifth Ave., a city-owned surface lot next to the Blake Transit Center and across from the downtown library.
Every unit is income-restricted. Households earning up to 80% of area median income qualify, and about a third of the apartments are reserved for those under 30% of AMI. WEMU reports it will be the first all-affordable high-rise in the city.
Project Scope
SmithGroup designed the tower, which sets back on a two-story podium. The ground floor carries more than 6,000 square feet of retail in two storefronts plus the resident lobby, and the second floor holds a lounge, a classroom, a kids’ playroom and a fitness center. Units are one- and two-bedrooms. The building is all-electric, with geothermal as the primary heating and cooling source, which Related says is a first for the company nationally. No general contractor has been named publicly.
The site has been waiting a while. A YMCA with about 100 affordable rooms stood there from 1960 to 2005, the building came down in 2008, and the lot has been parking ever since. State environmental officials found petroleum compounds and metals in the fill, and a $1 million brownfield grant covers old foundations and contaminated soil.
The building’s name honors Adeline Thompson, who with her husband Robert opened DeLong’s Bar-B-Q Pit across from the farmers market in 1964.
Why It Matters
This is how deep-affordability towers get built now: in layers. MSHDA approved $118.6 million, mostly tied to 4% tax credits. The Michigan Strategic Fund added a brownfield plan worth up to about $30 million, and the city council approved up to $35 million in general obligation bonds backed by its affordable housing millage. The housing commission says no other Michigan city has issued bonds that way.
Watch the budget line. The state put total investment at $209.4 million in May, the city said $215 million in March, and DBusiness headlined the groundbreaking at $225 million. Delivery is expected in 2028. If the number keeps climbing, the layered funding stack is where the strain will show.
Project Team & Details
| Developer | Related Midwest; Ann Arbor Housing Commission (Ann Arbor Housing Development Corporation) |
|---|
| Owner / Client | Fifth Avenue MI LDHA LLC (Ann Arbor Housing Development Corporation and Related Midwest) |
|---|
| Architect | SmithGroup |
|---|
| Status | Under Construction |
|---|
| Funding Source | Mixed |
|---|