The Stone Arch Bridge rehabilitation in Minneapolis finished early. MnDOT reopened the full 2,100-foot crossing on July 21, 2025, after the public had been told to expect fall 2025 or spring 2026, and the agency now lists the $38.5 million job as complete.
That’s an uncommon result for masonry repair on an 1883 railroad bridge standing in the Mississippi River.
Project Scope
James J. Hill built the 21-arch granite and limestone structure for his railroad. The last passenger train crossed in 1978, and the deck has carried pedestrians and cyclists since the 1990s. MnDOT owns it.
LHB led design, with Collins Engineers handling the underwater pier repairs. LHB’s project page also credits HNTB, WJE, SRF and Braun Intertec. Kraemer North America was the lead contractor, according to local reporting when the closure began in April 2024.
The work was unglamorous. Crews repointed mortar across the whole bridge, pressure-grouted the joints, replaced damaged stone faces and placed riprap around the piers. LHB puts the numbers at 500 tons of deteriorated stone removed and replaced, 21.4 miles of joints repointed on the arch undersides, and 867 stones re-faced. The designers found three quarry sources to match the historic stone. They also built a digital twin from drone data, which gives MnDOT a stone-by-stone record of roughly 19,000 limestone blocks and 4,000 granite ones.
Kraemer took the bridge one half at a time, starting on the St. Anthony Main side, so part of the deck stayed open to walkers through the first season.
Why It Matters
Start with the estimate history, which LHB has published with unusual candor. A 2018 scoping study put repairs at $13 million. The engineer’s estimate reached $25 million. The low bid came in around $40 million. MnDOT’s figure for the finished project is $38.5 million, and CBS News reported that $33.3 million of it was federal money.
That’s a tripling between scoping and bid on a structure the owner had been assessing since 2017. A 2020 drawdown at the Upper St. Anthony Falls lock gave engineers a look at piers that are normally underwater, and the number kept climbing afterward. Owners of other 19th-century masonry bridges should read that sequence closely before they publish an early figure.
The schedule went the other way. Nobody was hurt on the job, CBS reported, and the reopening beat the last public forecast by most of a year.
MnDOT says the repairs slow the deterioration. They don’t end it. The digital twin is the part of this job that should still be earning its fee in 2050.
Related coverage & projects
Project Team & Details
| Owner / Client | Minnesota Department of Transportation (MnDOT) |
|---|
| Consultants | LHB (Lead Design Engineer) Collins Engineers (Underwater Pier Repairs) HNTB (Design Team Member) WJE (Design Team Member) SRF Consulting Group (Design Team Member) Braun Intertec (Design Team Member) |
|---|
| General Contractor | Kraemer North America |
|---|
| Status | Completed |
|---|
| Delivery Method | Design-Bid-Build |
|---|
| Funding Source | Public (Federal) |
|---|