Warsaw’s skyline is mostly offices and hotels. Roma Tower is a bet that the city’s richest buyers want to live up there too. On Oct. 2, 2026, the developer group signed a construction contract with a consortium of Strabag and TKT Engineering for the 170-meter residential skyscraper at Emilii Plater and Nowogrodzka streets, a few blocks from the Palace of Culture and Science.
The contract is worth about PLN 840 million net (roughly €200 million, or about $224 million). It’s a lump sum, partly indexed to an agreed cost index, with provisions for changes in defined cases. Strabag calls it the largest commercial building contract it has signed in Poland.
Project Scope
The tower rises 48 floors above ground over six basement levels and holds 357 apartments pitched at the ultra-luxury end of the market. The site is the block bounded by Emilii Plater, Nowogrodzka and ÅšwiÄ™tej Barbary streets. The consortium’s scope covers the underground and above-ground structure, building services and the landscaping around the tower, and it has 50 months from site handover to finish. Work was set to start in October 2026.
Juvenes-Projekt, led by Jacek Åšwiderski, is the architect. Italian design house Pininfarina is handling the interior concept for the common areas and apartment finishes. Resident amenities include a wellness zone with a 25-meter pool and a private cinema room. The project already holds a three-star Fitwel rating, which the developers say is a first for a Polish residential building, and it’s pursuing BREEAM certification.
The ownership side changed alongside the contract. Czech investment group AKIPIA joined BBI Development, Liebrecht & wooD and the Pro Bonum Foundation, taking over a stake previously held through another vehicle. BBI, which has worked on the site since 2011, plans to keep roughly 45% and remains lead developer. The official launch, final renderings and apartment sales are planned for 2027.
Why It Matters
Fifteen years from first plans to a signed build contract tells you how hard it is to get a residential supertall-adjacent tower financed in central Warsaw. Bringing in a new equity partner at the same moment the GC deal closed isn’t a coincidence; it’s how the capital stack got finished.
Fifty months is a long program, and sales won’t open until 2027, so the developers are carrying market risk well into the decade. For Strabag the logic is simpler. It’s already building Upper One nearby, and keeping cranes, crews and supply chains in the same few blocks is where high-rise margin usually comes from.
Project Team & Details
| Developer | BBI Development |
|---|
| Owner / Client | BBI Development / Liebrecht & wooD / Pro Bonum Foundation / AKIPIA (joint venture) |
|---|
| Architect | Juvenes-Projekt (interiors concept: Pininfarina) |
|---|
| General Contractor | Strabag (consortium with TKT Engineering) |
|---|
| Status | Planned |
|---|
| Sustainability Certification | Fitwel (3-star); BREEAM (targeted) |
|---|
| Funding Source | Private |
|---|